United States › Grid › Interconnection queues › New Hampshire
OTHER · ISO-NEBiomass Project
Biomass Project is a 45.0 MW other request withdrawn in the ISO-NE interconnection queue, in Hillsborough County, New Hampshire.
Queue statusWithdrawn / abandoned
- PlanningQueued May 2007 (completed)
- Withdrawn / abandonedMay 2009 (project stopped here)
- Consented (not reached)
- Construction (not reached)
- Operating (not reached)
- Closed (not reached)
Request details
- Queue ID
- 212
- Grid region
- ISO-NE (New England)
- Connection point (POI)
- PSNH K-165 115 kV line
- Location
- Hillsborough County, New Hampshire
- Technology
- Other: 45.0 MW
- Total requested
- 45.0 MW
- Service type
- Other
- Queue status
- Withdrawn
- Entered queue
- 15 May 2007
- Proposed online date
- February 2010
- Withdrawn
- May 2009
Location
Marker shows the centre of Hillsborough County; the queue data does not give exact sites.
Power plants in New Hampshire · Transmission lines in New Hampshire
Other requests in Hillsborough County
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem