United States βΊ Grid βΊ Interconnection queues
OCTARY USA Β· INTERCONNECTION QUEUESCompleted queue projects in ERCOT (Texas) (2017 requests)
Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.
Map
Requests
| Project | Capacity | Status |
|---|---|---|
| Aviator Wind Onshore wind Β· Apex Clean |
525 MW | |
| High Lonesome Wind Onshore wind Β· Enel |
450 MW | |
| TG East Wind Onshore wind Β· Northrenew |
336 MW | |
| Prospero Solar*** Solar Β· Longroad Energy |
300 MW | |
| Ranchero Wind Onshore wind Β· Scout Clean Energy |
300 MW | |
| Titan Solar Solar Β· SE Titan, LLC |
270 MW | |
| Greasewood Solar Solar Β· Concho Bluff, LLC |
255 MW | |
| Phoebe Solar Solar Β· Longroad Energy |
250 MW | |
| Galloway Solar Solar Β· 8minutenergy |
250 MW | |
| Cranel Wind Onshore wind Β· Eon |
220 MW | |
| Vera Wind Onshore wind Β· Longroad Energy |
209 MW | |
| McLean (Shakes) Solar Solar Β· Cypress Creek Renewables |
206 MW | |
| East Raymond Wind (El Rayo) Onshore wind Β· Eon |
202 MW | |
| Anson Solar 1 Solar Β· Anson Solar Center, LLC |
202 MW | |
| Morrow Lake Solar Solar + storage Β· Morrow Lake Solar, LLC |
201 MW | |
| Montgomery Ranch Wind Onshore wind Β· RWE Renewables Development, LLC |
200 MW | |
| Rambler Solar Solar Β· Rambler Solar |
200 MW | |
| Queen Solar Phase I Solar Β· Roadrunner Solar Project, LLC |
200 MW | |
| Impact Solar Solar Β· IMPACT SOLAR 1 LLC |
199 MW | |
| Aragorn Solar Solar Β· IP Aragorn, LLC |
187 MW | |
| Oberon Solar Solar Β· OBERON SOLAR IA LLC |
180 MW | |
| Chalupa Wind Onshore wind Β· Acciona |
174 MW | |
| Gopher Creek Wind Onshore wind Β· Terna Energy |
158 MW | |
| White Mesa Wind Onshore wind Β· White Mesa Wind, LLC |
152 MW | |
| Lily Solar Solar Β· Lily Solar, LLC |
148 MW | |
| Nebula Solar Solar Β· Rayos Del Sol Solar Project, LLC |
138 MW | |
| Roadrunner Crossing Wind SLF Wind + storage Β· Roadrunner Crossing Wind Farm, LLC |
128 MW | |
| Coniglio Solar Solar Β· BT Coniglio Solar, LLC |
126 MW | |
| Wagyu Solar Solar Β· Cypress Creek Renewables |
120 MW | |
| Rowland Solar I Solar Β· Cutlass Solar LLC |
102 MW | |
| Karankawa 2 Wind Onshore wind Β· Avangrid |
101 MW | |
| Lignin (SJRR) Gas Β· SJRR Power LLC |
100 MW | |
| Old Bloomington Road Gas Β· Castleman Power |
100 MW | |
| Blue Summit II Wind + storage Β· Nextera |
99.4 MW | |
| Phoenix Solar Solar Β· G.S.E. ONE LLC |
82.3 MW | |
| Longbow Solar Solar Β· Longbow Solar, LLC |
78.2 MW | |
| Rippey Solar Solar Β· BT Cooke Solar, LLC |
59.8 MW | |
| Hidalgo II Wind Onshore wind Β· EDP Renewables |
51.0 MW | |
| Brightside Solar Solar Β· Brightside Solar, LLC |
50.0 MW | |
| Capricorn IV repower Onshore wind |
9.0 MW |
Capacity in the queue by state
Click a state to drill down.
By grid region
ISO/RTO markets and the non-ISO West and Southeast.
- Southeast (non-ISO utilities)82 Β· 8,124 MW
- ERCOT (Texas)40 Β· 7,316 MW
- MISO (Midcontinent)33 Β· 5,494 MW
- West (non-ISO utilities)46 Β· 3,321 MW
- PJM (Mid-Atlantic, Midwest)72 Β· 3,127 MW
- SPP (Southwest Power Pool)13 Β· 1,934 MW
- CAISO (California)9 Β· 1,239 MW
- NYISO (New York)12 Β· 598 MW
- ISO-NE (New England)9 Β· 242 MW
Requests by year joined
Capacity of requests in this view, by the year they entered the queue. Click a year.
Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines Β· Planned power plants (EIA)