SOLAR Β· ERCOTOberon Solar
Oberon Solar is a 180 MW solar request built and operating in the ERCOT interconnection queue, in Ector County, Texas.
Request details
- Queue ID
- 19INR0083
- Grid region
- ERCOT (Texas)
- Developer
- OBERON SOLAR IA LLC
- Connection point (POI)
- tap 138kV 1292 Ectorharp - 1013 Wolf
- Location
- Ector County, Texas
- Technology
- Solar: 180 MW
- Total requested
- 180 MW
- Study phase
- IA
- Queue status
- Operational
- Entered queue
- 30 May 2017
- Agreement signed
- 11 October 2018
- Proposed online date
- July 2020
- Came online
- July 2020
Location
Marker shows the centre of Ector County; the queue data does not give exact sites.
Other requests in Ector County
- Greyhound SolarSolar Β· 336 MW Β· agreement signed
- Sisters SolarSolar + storage Β· 302 MW Β· agreement signed
- Greyhound Solar - Phase ESolar Β· 151 MW Β· agreement signed
- Greyhound Solar - Phase FSolar Β· 102 MW Β· agreement signed
- Apple BESSBattery storage Β· 9.9 MW Β· agreement signed
- Gypsum Plains SolarSolar + storage Β· 503 MW Β· in study
- Velociraptor BESS IISolar + storage Β· 261 MW Β· in study
- Velociraptor BESS ISolar + storage Β· 261 MW Β· in study
- Van Zandt Energy StorageBattery storage Β· 257 MW Β· in study
- Velociraptor Solar IISolar + storage Β· 252 MW Β· in study
- Velociraptor Solar ISolar + storage Β· 252 MW Β· in study
- Gypsum Plains StorageSolar + storage Β· 211 MW Β· in study
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem