United States › Grid › Interconnection queues › Texas

ONSHORE WIND · ERCOT

Karankawa 2 Wind

Karankawa 2 Wind is a 101 MW onshore wind request built and operating in the ERCOT interconnection queue, in San Patricio County, Texas.

Queue statusOperating
  1. PlanningQueued May 2017 (completed)
  2. ConsentedFeb 2018 (completed)
  3. Construction (completed)
  4. OperatingNov 2019 (current stage)
  5. Closed (not yet reached)

Request details

Queue ID
19INR0074
Grid region
ERCOT (Texas)
Developer
Avangrid
Connection point (POI)
tap 345kV 8455 Lon Hill - 5725 Pawnee
Location
San Patricio County, Texas
Technology
Wind: 101 MW
Total requested
101 MW
Study phase
IA
Queue status
Operational
Entered queue
11 May 2017
Agreement signed
8 February 2018
Proposed online date
December 2019
Came online
November 2019

Location

Marker shows the centre of San Patricio County; the queue data does not give exact sites.

Power plants in Texas · Transmission lines in Texas

Other requests in San Patricio County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem