United States βΊ Grid βΊ Interconnection queues βΊ Texas
SOLAR Β· ERCOTAnson Solar 1
Anson Solar 1 is a 202 MW solar request built and operating in the ERCOT interconnection queue, in Jones County, Texas.
Request details
- Queue ID
- 19INR0081
- Grid region
- ERCOT (Texas)
- Developer
- Anson Solar Center, LLC
- Connection point (POI)
- tap 345kV 68000 WShack - 68001 Clayton
- Location
- Jones County, Texas
- Technology
- Solar: 202 MW
- Total requested
- 202 MW
- Study phase
- IA
- Queue status
- Operational
- Entered queue
- 22 June 2017
- Agreement signed
- 5 June 2019
- Proposed online date
- December 2021
- Came online
- January 2022
Location
Marker shows the centre of Jones County; the queue data does not give exact sites.
Other requests in Jones County
- Funston SolarSolar Β· 351 MW Β· agreement signed
- Tiger SolarSolar Β· 251 MW Β· agreement signed
- Crowded Star SolarSolar + storage Β· 219 MW Β· agreement signed
- Crowded Star I BESSSolar + storage Β· 203 MW Β· agreement signed
- Anson Solar 2Solar + storage Β· 201 MW Β· agreement signed
- Crowded Star Solar IISolar + storage Β· 190 MW Β· agreement signed
- Anson BATSolar + storage Β· 154 MW Β· agreement signed
- Moccasin StorageSolar + storage Β· 603 MW Β· in study
- Skeeter SolarSolar Β· 251 MW Β· in study
- Hamby SolarSolar Β· 206 MW Β· in study
- Anson Solar Center, Phase IIISolar Β· 200 MW Β· in study
- Solara BESS 2Battery storage Β· 150 MW Β· in study
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem