United States › Grid › Interconnection queues › Texas
SOLAR · ERCOTMcLean (Shakes) Solar
McLean (Shakes) Solar is a 206 MW solar request built and operating in the ERCOT interconnection queue, in Zavala County, Texas.
Request details
- Queue ID
- 19INR0073
- Grid region
- ERCOT (Texas)
- Developer
- Cypress Creek Renewables
- Connection point (POI)
- 8283 Asherton 138kV
- Location
- Zavala County, Texas
- Technology
- Solar: 206 MW
- Total requested
- 206 MW
- Study phase
- IA
- Queue status
- Operational
- Entered queue
- 2 May 2017
- Agreement signed
- 26 October 2018
- Proposed online date
- September 2023
- Came online
- September 2023
Location
Marker shows the centre of Zavala County; the queue data does not give exact sites.
Other requests in Zavala County
- Flying Kite SolarSolar + storage · 80.4 MW · agreement signed
- Bramble Energy CenterBattery storage · 225 MW · in study
- SunShiner ESSBattery storage · 200 MW · in study
- Flying Kite BessSolar + storage · 105 MW · in study
- La Mancha Storage SLFSolar + storage · 40.9 MW · in study
- La Mancha Solar SLFSolar + storage · 40.9 MW · in study
- GirasolSolar · 200 MW · withdrawn
- OCI SunShiner SolarSolar · 130 MW · withdrawn
- Peridot StorageBattery storage · 50.5 MW · withdrawn
- BARTLESVILLE SolarSolar · 4.3 MW · withdrawn
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem