GAS Β· ERCOT

Lignin (SJRR)

Lignin (SJRR) is a 100 MW gas request built and operating in the ERCOT interconnection queue, in Harris County, Texas.

Queue statusOperating
  1. PlanningQueued Apr 2017 (completed)
  2. ConsentedSep 2019 (completed)
  3. Construction (completed)
  4. OperatingJun 2022 (current stage)
  5. Closed (not yet reached)

Request details

Queue ID
19INR0056
Grid region
ERCOT (Texas)
Developer
SJRR Power LLC
Connection point (POI)
40260 Chamon 138kV
Location
Harris County, Texas
Technology
Gas: 100 MW
Total requested
100 MW
Study phase
IA
Queue status
Operational
Entered queue
23 April 2017
Agreement signed
20 September 2019
Proposed online date
June 2022
Came online
June 2022

Location

Marker shows the centre of Harris County; the queue data does not give exact sites.

Power plants in Texas Β· Transmission lines in Texas

Other requests in Harris County