🔌 EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more → Skip to main content

United States › Grid › Interconnection queues › Texas

ONSHORE WIND · ERCOT

Chalupa Wind

Chalupa Wind is a 174 MW onshore wind request built and operating in the ERCOT interconnection queue, in Cameron County, Texas.

Queue statusOperating
  1. PlanningQueued Dec 2017 (completed)
  2. ConsentedSep 2018 (completed)
  3. Construction (completed)
  4. OperatingJun 2021 (current stage)
  5. Closed (not yet reached)

Request details

Queue ID
20INR0042
Grid region
ERCOT (Texas)
Developer
Acciona
Connection point (POI)
8640 Kelvin 138kV
Location
Cameron County, Texas
Technology
Wind: 174 MW
Total requested
174 MW
Study phase
IA
Queue status
Operational
Entered queue
21 December 2017
Agreement signed
28 September 2018
Proposed online date
April 2021
Came online
June 2021

Location

Marker shows the centre of Cameron County; the queue data does not give exact sites.

Power plants in Texas · Transmission lines in Texas

Other requests in Cameron County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem