SOLAR Β· ERCOT

Phoebe Solar

Phoebe Solar is a 250 MW solar request built and operating in the ERCOT interconnection queue, in Winkler County, Texas.

Queue statusOperating
  1. PlanningQueued Jan 2017 (completed)
  2. ConsentedMar 2018 (completed)
  3. Construction (completed)
  4. OperatingNov 2019 (current stage)
  5. Closed (not yet reached)

Request details

Queue ID
19INR0029
Grid region
ERCOT (Texas)
Developer
Longroad Energy
Connection point (POI)
11260 Dune Switch
Location
Winkler County, Texas
Technology
Solar: 250 MW
Total requested
250 MW
Study phase
IA
Queue status
Operational
Entered queue
25 January 2017
Agreement signed
5 March 2018
Proposed online date
October 2019
Came online
November 2019

Location

Marker shows the centre of Winkler County; the queue data does not give exact sites.

Power plants in Texas Β· Transmission lines in Texas

Other requests in Winkler County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem