Ranchero Wind

Ranchero Wind is a 300 MW onshore wind request built and operating in the ERCOT interconnection queue, in Crockett County, Texas.

Queue statusOperating
  1. PlanningQueued Jun 2017 (completed)
  2. ConsentedMay 2018 (completed)
  3. Construction (completed)
  4. OperatingJul 2019 (current stage)
  5. Closed (not yet reached)

Request details

Queue ID
20INR0011
Grid region
ERCOT (Texas)
Developer
Scout Clean Energy
Connection point (POI)
7053 Noelke 345kV
Location
Crockett County, Texas
Technology
Wind: 300 MW
Total requested
300 MW
Study phase
IA
Queue status
Operational
Entered queue
22 June 2017
Agreement signed
2 May 2018
Proposed online date
April 2020
Came online
July 2019

Location

Marker shows the centre of Crockett County; the queue data does not give exact sites.

Power plants in Texas · Transmission lines in Texas

Other requests in Crockett County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem