United States › Grid › Interconnection queues › Texas
ONSHORE WIND · ERCOTRanchero Wind
Ranchero Wind is a 300 MW onshore wind request built and operating in the ERCOT interconnection queue, in Crockett County, Texas.
Request details
- Queue ID
- 20INR0011
- Grid region
- ERCOT (Texas)
- Developer
- Scout Clean Energy
- Connection point (POI)
- 7053 Noelke 345kV
- Location
- Crockett County, Texas
- Technology
- Wind: 300 MW
- Total requested
- 300 MW
- Study phase
- IA
- Queue status
- Operational
- Entered queue
- 22 June 2017
- Agreement signed
- 2 May 2018
- Proposed online date
- April 2020
- Came online
- July 2019
Location
Marker shows the centre of Crockett County; the queue data does not give exact sites.
Other requests in Crockett County
- Midnight Sun Energy StorageBattery storage · 510 MW · agreement signed
- Big Sampson WindOnshore wind · 265 MW · agreement signed
- Blue Sky SolSolar + storage · 101 MW · agreement signed
- Gridline SolarSolar · 400 MW · in study
- Ranchero BESSBattery storage · 150 MW · in study
- Black Bear SolarSolar + storage · 103 MW · in study
- Black Bear BESSSolar + storage · 51.2 MW · in study
- Shamrock II WindOnshore wind · 257 MW · suspended
- High Lonesome WindOnshore wind · 450 MW · built
- White Mesa 2 WindOnshore wind · 348 MW · built
- ShamrockOnshore wind · 224 MW · built
- White Mesa WindOnshore wind · 152 MW · built
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem