Midnight Sun Energy Storage

Midnight Sun Energy Storage is a 510 MW battery storage request with a signed interconnection agreement in the ERCOT interconnection queue, in Crockett County, Texas.

Queue statusConsented
  1. PlanningQueued Dec 2022 (completed)
  2. ConsentedJul 2025 (current stage)
  3. Construction (not yet reached)
  4. OperatingTarget Jun 2028 (not yet reached)
  5. Closed (not yet reached)

Request details

Queue ID
24INR0442
Grid region
ERCOT (Texas)
Developer
Midnight Sun Energy Storage, LLC
Connection point (POI)
6601 Rio Pecos 138kV
Location
Crockett County, Texas
Technology
Battery: 510 MW
Total requested
510 MW
Study phase
SS Completed, FIS Started, IA
Queue status
Active
Entered queue
7 December 2022
Agreement signed
14 July 2025
Proposed online date
June 2028

Location

Marker shows the centre of Crockett County; the queue data does not give exact sites.