United States β€Ί Grid β€Ί Interconnection queues

OCTARY USA Β· INTERCONNECTION QUEUES

Withdrawn queue requests in CAISO (California) (2021 requests)

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown22082.8 GW
Active in queue66.9 GW138 requests
Agreement signed35.4 GW68 requests
Withdrawn22082.8 GW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

220 requests Β· page 1 of 5
ProjectCapacityStatusLocationRegionQueuedOnline
Eternal 2
Other
2,851 MWWithdrawn / abandoned Riverside, CACAISO Apr 2021target 2031
Islay
Wind + storage
2,275 MWWithdrawn / abandoned San Luis Obispo, CACAISO Apr 2021target 2034
Lava Ridge Wind
Wind + storage
1,666 MWWithdrawn / abandoned Lincoln, IDCAISO Apr 2021target 2025
Hyder
Solar + storage
1,648 MWWithdrawn / abandoned Maricopa, AZCAISO Apr 2021target 2035
Empire
Battery storage
1,647 MWWithdrawn / abandoned San Bernardino, CACAISO Apr 2021target 2024
Salinan Energy
Wind + storage
1,509 MWWithdrawn / abandoned San Luis Obispo, CACAISO Apr 2021target 2032
Bravo Wind
Offshore wind
1,465 MWWithdrawn / abandoned San Luis Obispo, CACAISO Apr 2021target 2034
Salmon Falls Wind
Wind + storage
1,356 MWWithdrawn / abandoned Twin Falls, IDCAISO Apr 2021target 2026
Colima Hybrid Solar
Solar + storage
1,212 MWWithdrawn / abandoned Kern, CACAISO Apr 2021target 2026
Wingtip Solar 2
Solar + storage
1,123 MWWithdrawn / abandoned Merced, CACAISO Apr 2021target 2027
Red Star Grizzly Offshore Wind
Offshore wind
1,040 MWWithdrawn / abandoned San Luis Obispo, CACAISO Apr 2021target 2028
La Paz 2
Solar + storage
1,034 MWWithdrawn / abandoned Maricopa, AZCAISO Apr 2021target 2028
Water Canyon Wind
Onshore wind
1,029 MWWithdrawn / abandoned San Luis Obispo, CACAISO Apr 2021target 2028
Adobe Flats
Solar + storage
1,024 MWWithdrawn / abandoned La Paz, AZCAISO Apr 2021target 2025
Bellefield Solar 4
Solar + storage
1,017 MWWithdrawn / abandoned Kern, CACAISO Apr 2021target 2025
Eolica De Rumorosa
Onshore wind
941 MWWithdrawn / abandoned Tecate Baja California Mexico, CACAISO Apr 2021target 2035
Primrose Hybrid
Solar + storage
912 MWWithdrawn / abandoned Maricopa, AZCAISO Apr 2021target 2025
Three Rocks
Solar + storage
878 MWWithdrawn / abandoned CACAISO Apr 2021target 2024
Solar Farm Energy Center
Solar + storage
822 MWWithdrawn / abandoned Tulare, CACAISO Apr 2021target 2026
Hadselville
Solar + storage
816 MWWithdrawn / abandoned Stanislaus, CACAISO Apr 2021target 2025
Estanislau Solar Storage
Solar + storage
816 MWWithdrawn / abandoned San Joaquin, CACAISO Apr 2021target 2024
Yeager Mustang
Solar + storage
815 MWWithdrawn / abandoned Kern, CACAISO Apr 2021target 2027
Muscat
Battery storage
772 MWWithdrawn / abandoned CACAISO Apr 2021target 2024
Sur Vista
Solar + storage
718 MWWithdrawn / abandoned Kern, CACAISO Apr 2021target 2024
Juglans Energy Storage
Battery storage
711 MWWithdrawn / abandoned Solano, CACAISO Apr 2021target 2031
Adastra Hybrid Solar
Solar + storage
709 MWWithdrawn / abandoned Tulare, CACAISO Apr 2021target 2025
Edison Drive Energy Storage
Battery storage
672 MWWithdrawn / abandoned Ventura, CACAISO Apr 2021target 2024
Huxley Solar
Solar + storage
671 MWWithdrawn / abandoned Los Angeles, CACAISO Apr 2021target 2027
Ashanti Hybrid Solar
Solar + storage
650 MWWithdrawn / abandoned Riverside, CACAISO Apr 2021target 2024
Seaglass Offshore Wind
Offshore wind
629 MWWithdrawn / abandoned San Luis Obispo, CACAISO Apr 2021target 2032
Natura
Other
623 MWWithdrawn / abandoned Riverside, CACAISO Apr 2021target 2025
Charger Storage
Battery storage
616 MWWithdrawn / abandoned San Diego, CACAISO Apr 2021target 2025
Blue Oak Storage
Battery storage
616 MWWithdrawn / abandoned San Joaquin, CACAISO Apr 2021target 2025
Resonate
Solar + storage
615 MWWithdrawn / abandoned Los Angeles, CACAISO Apr 2021target 2024
Osito Energy
Solar + storage
613 MWWithdrawn / abandoned Placer, CACAISO Apr 2021target 2024
Voltron
Solar + storage
612 MWWithdrawn / abandoned Los Angeles, CACAISO Apr 2021target 2024
Red Arch Hybrid Solar
Solar + storage
608 MWWithdrawn / abandoned Kern, CACAISO Apr 2021target 2025
Europa Energy Center
Solar + storage
607 MWWithdrawn / abandoned Kern, CACAISO Apr 2021target 2025
Fuerte Energy Storage
Battery storage
554 MWWithdrawn / abandoned San Bernardino, CACAISO Apr 2021target 2024
Alum Geothermal
Geothermal
530 MWWithdrawn / abandoned Esmeralda, NVCAISO Apr 2021target 2025
Appellation
Battery storage
515 MWWithdrawn / abandoned CACAISO Apr 2021target 2024
MT Baldy Energy Storage
Battery storage
513 MWWithdrawn / abandoned San Bernardino, CACAISO Apr 2021target 2031
Menilles
Solar + storage
511 MWWithdrawn / abandoned Fresno, CACAISO Apr 2021target 2024
Blythe BESS
Battery storage
510 MWWithdrawn / abandoned Riverside, CACAISO Mar 2021target 2022
Goodall Storage
Battery storage
510 MWWithdrawn / abandoned San Bernardino, CACAISO Apr 2021target 2023
Dolores
Battery storage
510 MWWithdrawn / abandoned San Clara, CACAISO Apr 2021target 2025
Winoka Hybrid Solar
Solar + storage
508 MWWithdrawn / abandoned Kern, CACAISO Apr 2021target 2024
Stirling Bridge
Solar + storage
507 MWWithdrawn / abandoned San Joaquin, CACAISO Apr 2021target 2031
Bison Peak
Battery storage
506 MWWithdrawn / abandoned Kern, CACAISO Apr 2021target 2025
Ada Energy Storage
Battery storage
505 MWWithdrawn / abandoned Santa Clara, CACAISO Apr 2021target 2034
Page 1 of 5

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines Β· Planned power plants (EIA)