🔌 EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more → Skip to main content

United States › Grid › Interconnection queues › California

SOLAR + STORAGE · CAISO

Stirling Bridge

Stirling Bridge is a 507 MW solar + storage request withdrawn in the CAISO interconnection queue, in San Joaquin County, California, connecting to PGAE.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Apr 2021 (completed)
  2. Withdrawn / abandonedMar 2024 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
1916
Grid region
CAISO (California)
Utility / transmission owner
PGAE
Connection point (POI)
Bellota 115 kV
Location
San Joaquin County, California
Technology
Solar: 257 MW · Battery: 250 MW
Total requested
507 MW
Service type
Network resource (NRIS)
Study phase
System Impact Study
Queue status
Withdrawn
Entered queue
15 April 2021
Proposed online date
March 2031
Withdrawn
March 2024

Location

Marker shows the centre of San Joaquin County; the queue data does not give exact sites.

Power plants in California · Transmission lines in California

Other requests in San Joaquin County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem