WIND + STORAGE Β· CAISOLava Ridge Wind
Lava Ridge Wind is a 1,666 MW wind + storage request withdrawn in the CAISO interconnection queue, in Lincoln County, Idaho, connecting to DSLK.
Queue statusWithdrawn / abandoned
- PlanningQueued Apr 2021 (completed)
- Withdrawn / abandonedJan 2023 (project stopped here)
- Consented (not reached)
- Construction (not reached)
- Operating (not reached)
- Closed (not reached)
Request details
- Queue ID
- 2151
- Grid region
- CAISO (California)
- Utility / transmission owner
- DSLK
- Connection point (POI)
- Harry Allen-Eldorado 500 kV
- Location
- Lincoln County, Idaho
- Technology
- Wind: 1,156 MW Β· Battery: 510 MW
- Total requested
- 1,666 MW
- Service type
- Network resource (NRIS)
- Study phase
- Feasibility Study
- Queue status
- Withdrawn
- Entered queue
- 15 April 2021
- Proposed online date
- December 2025
- Withdrawn
- January 2023
Location
Marker shows the centre of Lincoln County; the queue data does not give exact sites.
Other requests in Lincoln County
- Solar + storage project C2-54, Lincoln CountySolar + storage Β· 200 MW Β· agreement signed
- Hydro project 687, Lincoln CountyHydro Β· 4.8 MW Β· built
- Other project 348, Lincoln CountyOther Β· 4.5 MW Β· built
- Hydro project 494, Lincoln CountyHydro Β· 1.2 MW Β· built
- Hydro project 606, Lincoln CountyHydro Β· 1.1 MW Β· built
- Hydro project 599, Lincoln CountyHydro Β· 1.0 MW Β· built
- Hydro project hist_q34, Lincoln CountyHydro Β· 0.9 MW Β· built
- Other project GOB2, Lincoln CountyOther Β· 0.9 MW Β· built
- Other project SHS2, Lincoln CountyOther Β· 0.6 MW Β· built
- Hydro project 515, Lincoln CountyHydro Β· 0.5 MW Β· built
- Other project SHCS, Lincoln CountyOther Β· 0.4 MW Β· built
- Other project SGBR, Lincoln CountyOther Β· 0.4 MW Β· built
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem