🔌 EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more → Skip to main content

United States › Grid › Interconnection queues › Idaho

SOLAR + STORAGE · WEST

Solar + storage project C2-54, Lincoln County

Solar + storage project C2-54, Lincoln County is a 200 MW solar + storage request with a signed interconnection agreement in the West interconnection queue, in Lincoln County, Idaho, connecting to PacifiCorp.

Queue statusConsented
  1. PlanningQueued May 2022 (completed)
  2. Consented (current stage)
  3. Construction (not yet reached)
  4. OperatingTarget Dec 2036 (not yet reached)
  5. Closed (not yet reached)

Request details

Queue ID
C2-54
Grid region
West (non-ISO utilities)
Utility / transmission owner
PacifiCorp
Developer
Star Lake Solar, LLC
Connection point (POI)
Midpoint substation
Location
Lincoln County, Idaho
Technology
Solar: 200 MW · Battery
Total requested
200 MW
Service type
Network resource (NRIS)
Study phase
LGIA Executed 11/10/2025
Queue status
Active
Entered queue
6 May 2022
Proposed online date
December 2036

Location

Marker shows the centre of Lincoln County; the queue data does not give exact sites.

Power plants in Idaho · Transmission lines in Idaho

Other requests in Lincoln County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem