United States › Grid › Interconnection queues › Idaho
SOLAR + STORAGE · WESTSolar + storage project C2-54, Lincoln County
Solar + storage project C2-54, Lincoln County is a 200 MW solar + storage request with a signed interconnection agreement in the West interconnection queue, in Lincoln County, Idaho, connecting to PacifiCorp.
Queue statusConsented
- PlanningQueued May 2022 (completed)
- Consented (current stage)
- Construction (not yet reached)
- OperatingTarget Dec 2036 (not yet reached)
- Closed (not yet reached)
Request details
- Queue ID
- C2-54
- Grid region
- West (non-ISO utilities)
- Utility / transmission owner
- PacifiCorp
- Developer
- Star Lake Solar, LLC
- Connection point (POI)
- Midpoint substation
- Location
- Lincoln County, Idaho
- Technology
- Solar: 200 MW · Battery
- Total requested
- 200 MW
- Service type
- Network resource (NRIS)
- Study phase
- LGIA Executed 11/10/2025
- Queue status
- Active
- Entered queue
- 6 May 2022
- Proposed online date
- December 2036
Location
Marker shows the centre of Lincoln County; the queue data does not give exact sites.
Other requests in Lincoln County
- Hydro project 687, Lincoln CountyHydro · 4.8 MW · built
- Other project 348, Lincoln CountyOther · 4.5 MW · built
- Hydro project 494, Lincoln CountyHydro · 1.2 MW · built
- Hydro project 606, Lincoln CountyHydro · 1.1 MW · built
- Hydro project 599, Lincoln CountyHydro · 1.0 MW · built
- Hydro project hist_q34, Lincoln CountyHydro · 0.9 MW · built
- Other project GOB2, Lincoln CountyOther · 0.9 MW · built
- Other project SHS2, Lincoln CountyOther · 0.6 MW · built
- Hydro project 515, Lincoln CountyHydro · 0.5 MW · built
- Other project SHCS, Lincoln CountyOther · 0.4 MW · built
- Other project SGBR, Lincoln CountyOther · 0.4 MW · built
- Lava Ridge WindWind + storage · 1,666 MW · withdrawn
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem