Wingtip Solar 2

Wingtip Solar 2 is a 1,123 MW solar + storage request withdrawn in the CAISO interconnection queue, in Merced County, California, connecting to PGAE.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Apr 2021 (completed)
  2. Withdrawn / abandonedJan 2023 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
1944
Grid region
CAISO (California)
Utility / transmission owner
PGAE
Connection point (POI)
Los Banos Substation 500 kV
Location
Merced County, California
Technology
Solar: 562 MW · Battery: 562 MW
Total requested
1,123 MW
Service type
Network resource (NRIS)
Study phase
System Impact Study
Queue status
Withdrawn
Entered queue
15 April 2021
Proposed online date
June 2027
Withdrawn
January 2023

Location

Marker shows the centre of Merced County; the queue data does not give exact sites.

Power plants in California · Transmission lines in California

Other requests in Merced County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem