🔌 EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more → Skip to main content

United States › Grid › Interconnection queues › California

BATTERY STORAGE · CAISO

Ada Energy Storage

Ada Energy Storage is a 505 MW battery storage request withdrawn in the CAISO interconnection queue, in Santa Clara County, California, connecting to PGAE.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Apr 2021 (completed)
  2. Withdrawn / abandonedJul 2024 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
1894
Grid region
CAISO (California)
Utility / transmission owner
PGAE
Connection point (POI)
Monta Vista 230 kV
Location
Santa Clara County, California
Technology
Battery: 505 MW
Total requested
505 MW
Service type
Network resource (NRIS)
Study phase
System Impact Study
Queue status
Withdrawn
Entered queue
15 April 2021
Proposed online date
March 2034
Withdrawn
July 2024

Location

Marker shows the centre of Santa Clara County; the queue data does not give exact sites.

Power plants in California · Transmission lines in California

Other requests in Santa Clara County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem