SOLAR + STORAGE · CAISO

Colima Hybrid Solar

Colima Hybrid Solar is a 1,212 MW solar + storage request withdrawn in the CAISO interconnection queue, in Kern County, California, connecting to SCE.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Apr 2021 (completed)
  2. Withdrawn / abandonedDec 2022 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
2070
Grid region
CAISO (California)
Utility / transmission owner
SCE
Connection point (POI)
Pastoria Substation 230 kV
Location
Kern County, California
Technology
Solar: 606 MW · Battery: 606 MW
Total requested
1,212 MW
Service type
Network resource (NRIS)
Study phase
Feasibility Study
Queue status
Withdrawn
Entered queue
5 April 2021
Proposed online date
April 2026
Withdrawn
December 2022

Location

Marker shows the centre of Kern County; the queue data does not give exact sites.

Power plants in California · Transmission lines in California

Other requests in Kern County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem