Battery storage interconnection queue in the USA — page 9

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown2,226417.8 GW
Active in queue417.8 GW2,226 requests
Agreement signed76.1 GW459 requests
Withdrawn3,516554.5 GW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

2,226 requests · page 9 of 45
ProjectCapacityStatusLocationRegionQueuedOnline
Sherman Energy Storage
Battery storage
256 MWIn study Contra Costa, CACAISO Apr 2021target 2031
Gateway Energy Storage 2
Battery storage
256 MWIn study San Diego, CACAISO Apr 2021target 2035
Nautilus Heavy Storage
Battery storage · Nautilus Heavy Storage, LLC
256 MWIn study San Patricio, TXERCOT Dec 2023target 2028
Leaning Tree BESS
Battery storage
256 MWPaused / redesign Throckmorton, TXERCOT Nov 2023target 2026
Maleza Storage II
Battery storage · Brush Storage, LLC
256 MWIn study Wharton, TXERCOT Feb 2024target 2027
Lonesome Dove BESS
Battery storage
256 MWPaused / redesign Throckmorton, TXERCOT Nov 2023target 2026
Champs Elysees BESS
Battery storage · Champs Elysees Renewables, LLC
256 MWIn study Milam, TXERCOT Aug 2024target 2027
Nouveau BESS
Battery storage · RamZ BESS, LLC
256 MWIn study Brown, TXERCOT Aug 2024target 2027
Sandbar Energy Storage
Battery storage
256 MWIn study San Diego, CACAISO Apr 2021target 2030
Zeya BESS
Battery storage · BRP Zeya BESS LLC
255 MWAgreement signed Galveston, TXERCOT May 2021target 2026
PowerVault BESS
Battery storage · SMT Elm Mott BESS
255 MWIn study Mclennan, TXERCOT Mar 2024target 2027
Sandrift Storage 1
Battery storage
255 MWAgreement signed Riverside, CACAISO Apr 2021target 2030
Sandrift Storage 2
Battery storage
255 MWAgreement signed Riverside, CACAISO Apr 2021target 2031
Railway BESS
Battery storage
255 MWPaused / redesign Rusk, TXERCOT Jan 2023target 2026
Staked Plains BESS
Battery storage
255 MWPaused / redesign Lubbock, TXERCOT Mar 2023target 2026
Battery storage project GEN-2021-029, Linn County
Battery storage
254 MWIn study Linn, KSSPP May 2021target 2026
Grand Mesa BESS
Battery storage · PERRY GREEN POWER LLC
253 MWIn study Pecos, TXERCOT Aug 2024target 2027
Bayside 2 BESS
Battery storage
252 MWPaused / redesign Dewitt, TXERCOT Mar 2022
Greenwood Energy Storage
Battery storage
252 MWAgreement signed Los Angeles, CACAISO Apr 2021target 2032
Zorin Storage
Battery storage
252 MWAgreement signed Alameda, CACAISO Apr 2021target 2034
Little Ridge Storage
Battery storage · TX BESS B LLC
252 MWIn study Collin, TXERCOT May 2023target 2025
Eval Storage
Battery storage · Hecate Grid East Valley Storage LLC
252 MWAgreement signed Cameron, TXERCOT Oct 2020target 2028
Ogalalla Storage
Battery storage · Hecate Energy Ogalalla Solar LLC
252 MWIn study Castro, TXERCOT Jan 2024target 2028
Juniper Ridge BESS 2
Battery storage · Lazy U ESS 2
252 MWIn study Hardeman, TXERCOT Aug 2023target 2029
Juniper Ridge BESS 1
Battery storage · Lazy U ESS 1
252 MWIn study Hardeman, TXERCOT Sep 2023target 2029
Buffalo Creek BESS
Battery storage · Old 300 Storage Center, LLC
251 MWAgreement signed Fort Bend, TXERCOT Mar 2024target 2026
Mesa View Storage
Battery storage · Mesa View Storage, LLC
251 MWIn study Upton, TXERCOT Apr 2023target 2027
Althea Storage
Battery storage · Sugaree Solar LLC
251 MWAgreement signed Maverick, TXERCOT Feb 2025target 2028
Brela BESS LLC
Battery storage · Brela BESS LLC
251 MWIn study Wharton, TXERCOT Jan 2024target 2028
Fort Concho Energy storage
Battery storage · Rocky Mountain Energy Development, LLC
251 MWIn study Tom Green, TXERCOT Jan 2023target 2028
Cantaloupe Storage
Battery storage
251 MWPaused / redesign Reeves, TXERCOT Dec 2020
Rock Creek BESS
Battery storage · Flat Rock Energy Center, LLC
251 MWAgreement signed Kendall, TXERCOT Feb 2024target 2028
Tiger Storage
Battery storage
251 MWPaused / redesign Jones, TXERCOT Apr 2021
Parula Energy Center
Battery storage · Parula Energy Center
251 MWIn study Austin, TXERCOT May 2024target 2027
Bluegill BESS
Battery storage · Bluegill BESS, LLC
251 MWIn study Harris, TXERCOT Jun 2023target 2027
Medway Grid Battery Storage
Battery storage
250 MWAgreement signed Norfolk, MAISO-NE Mar 2019target 2025
Battery storage project 5RSC-2024-11, Morgan County
Battery storage
250 MWIn study Morgan, COWest Jan 2024target 2027
Battery storage project J3836, Eaton County
Battery storage
250 MWIn study Eaton, MIMISO Oct 2024target 2028
Ca-CO-250B
Battery storage
250 MWIn study El Paso, TXWest Jun 2025target 2029
Battery storage project J4167, Allegan County
Battery storage
250 MWIn study Allegan, MIMISO Sep 2025target 2030
Battery storage project J3845, Monroe County
Battery storage
250 MWIn study Monroe, MIMISO Nov 2024target 2029
Battery storage project GEN-2024-171, Tulsa County
Battery storage
250 MWIn study Tulsa, OKSPP Mar 2025target 2028
Battery storage project J2628, Huron County
Battery storage
250 MWIn study Huron, MIMISO Sep 2022target 2028
Battery storage project Company 237, Clark County
Battery storage
250 MWAgreement signed Clark, NVWest Jan 2023target 2026
Battery storage project J3883, Crawford County
Battery storage
250 MWIn study Crawford, ILMISO Feb 2025target 2030
Commerce Energy Storage
Battery storage
250 MWAgreement signed Los Angeles, CACAISO Apr 2019target 2026
Battery storage project 25-IC-1312, Coweta County
Battery storage
250 MWIn study Coweta, GASoutheast Apr 2025target 2028
Battery storage project J4198, Christian County
Battery storage
250 MWIn study Christian, ILMISO Sep 2025target 2030
Battery storage project AI1-149, Mchenry County
Battery storage
250 MWIn study Mchenry, ILPJM Sep 2022target 2025
Battery storage project AI2-068, Monmouth County
Battery storage
250 MWIn study Monmouth, NJPJM Feb 2023target 2026
Page 9 of 45

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines · Planned power plants (EIA)