United States › Grid › Interconnection queues › Texas

BATTERY STORAGE · ERCOT

Nouveau BESS

Nouveau BESS is a 256 MW battery storage request in interconnection study in the ERCOT interconnection queue, in Brown County, Texas.

Queue statusIn planning
  1. PlanningQueued Aug 2024 (current stage)
  2. Consented (not yet reached)
  3. Construction (not yet reached)
  4. OperatingTarget Dec 2027 (not yet reached)
  5. Closed (not yet reached)

Studies assess what grid upgrades the project would need and who pays for them. A signed interconnection agreement is the main step before construction.

Request details

Queue ID
27INR0291
Grid region
ERCOT (Texas)
Developer
RamZ BESS, LLC
Connection point (POI)
1444 Brown Switch - 3348 Russell Gap 345 kV Line
Location
Brown County, Texas
Technology
Battery: 256 MW
Total requested
256 MW
Study phase
SS Completed, FIS Started, No IA
Queue status
Active
Entered queue
16 August 2024
Proposed online date
December 2027

Location

Marker shows the centre of Brown County; the queue data does not give exact sites.

Power plants in Texas · Transmission lines in Texas

Other requests in Brown County