United States › Grid › Interconnection queues

OCTARY USA · INTERCONNECTION QUEUES

Queue requests in study in the USA — page 86

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown6,8521,550.1 GW
Active in queue2,001.0 GW9,187 requests
Agreement signed423.2 GW2,141 requests
Withdrawn24,2054,519.8 GW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

6,852 requests · page 86 of 138
ProjectCapacityStatusLocationRegionQueuedOnline
Buckaroo BESS
Battery storage · Weatherford BESS LLC
120 MWIn study Parker, TXERCOT May 2024target 2027
Wild Horse Desert Solar
Solar + storage · Wild Horse Desert Solar, LLC
120 MWIn study Dimmit, TXERCOT Dec 2024target 2028
Surplus; G736
Other
120 MWIn study Codington, SDMISO Oct 2023target 2026
Solar project AG2-516, Winnebago County
Solar · Kestrel Solar, LLC
120 MWIn study Winnebago, ILPJM Feb 2025target 2023
Solar + storage project GEN-2024-373, Choctaw County
Solar + storage
120 MWIn study Choctaw, OKSPP Mar 2025target 2029
Solar project GI-2024-10, Adams County
Solar
120 MWIn study Adams, COWest May 2024target 2027
Solar + storage project 2021-G3, Pinal County
Solar + storage
119 MWIn study Pinal, AZWest Apr 2021target 2023
Solar project 649, Muhlenberg County
Solar
119 MWIn study Muhlenberg, KYSoutheast Sep 2024target 2033
Tracy Solar Energy Center
Solar · Tracy Solar Energy Center, LLC
119 MWIn study Jefferson, NYNYISO Oct 2018target 2028
Pradera Solar
Solar + storage · Pradera Solar, LLC
118 MWIn study Webb, TXERCOT Jul 2021target 2027
Solar + storage project AI1-174, Stephenson County
Solar + storage
118 MWIn study Stephenson, ILPJM Sep 2022target 2028
Onshore wind project GEN-2023-088, Okfuskee County
Onshore wind
117 MWIn study Okfuskee, OKSPP Oct 2023target 2028
Battery storage project AH2-132, Salem County
Battery storage
117 MWIn study Salem, NJPJM Mar 2022target 2024
Solar project J3539, Alcona County
Solar
117 MWIn study Alcona, MIMISO Mar 2024target 2027
Roxton Solar
Solar + storage · Roxton Solar, LLC
117 MWIn study Lamar, TXERCOT Nov 2024target 2028
Shorebird Solar
Solar
117 MWPaused / redesign Crawford, PAPJM Mar 2019target 2025
Pioneer Hutt Solar
Solar
116 MWPaused / redesign Midland, TXERCOT Oct 2022
Butcherbird Solar
Solar · Butcherbird Solar, LLC
116 MWIn study Bell, TXERCOT Dec 2023target 2027
Pioneer Hutt Solar (Alternative POI)
Solar · NextEra Energy Interconnection Holdings LLC
116 MWIn study Midland, TXERCOT Jun 2023target 2028
Battery storage project GEN-2025-SR12, Noble County
Battery storage
116 MWIn study Noble, OKSPP May 2025target 2030
Marcos BESS
Solar + storage · GRS BESS Texas Eight LLC
116 MWIn study Victoria, TXERCOT Feb 2024target 2027
Solar project J2350, Pulaski County
Solar
116 MWIn study Pulaski, ARMISO Sep 2022target 2025
Amphion Solar Phase 3
Solar · Amphion Solar, LLC
115 MWIn study Atascosa, TXERCOT Apr 2025target 2029
Velado Storage SLF
Solar + storage · Velado Solar, LLC
115 MWIn study Dimmit, TXERCOT Nov 2024target 2028
Velado Solar SLF
Solar + storage · Velado Solar, LLC
115 MWIn study Dimmit, TXERCOT Nov 2024target 2028
Gas project BHBE G25, Pennington County
Gas · Black Hills Power Inc.
115 MWIn study Pennington, SDWest Jun 2024target 2026
Battery storage project GEN-2024-295, Eddy County
Battery storage
115 MWIn study Eddy, NMSPP Mar 2025target 2030
SR Bacon II Solar
Solar
115 MWIn study Bacon, GASoutheast Sep 2023target 2027
Battery storage project IA-PNM-2025-12, Cibola County
Battery storage
115 MWIn study Cibola, NMWest Mar 2025target 2027
Battery storage project J3523, Barron County
Battery storage
115 MWIn study Barron, WIMISO Apr 2024target 2028
Solar + storage project J2382, Randolph County
Solar + storage
115 MWIn study Randolph, MOMISO Sep 2022target 2026
Gas project 40603, Laramie County
Gas · Cheyenne Light, Fuel and Power Company
115 MWIn study Laramie, WYWest Aug 2025target 2028
Solar project AG2-583, Cumberland County
Solar · Boston Hill Solar, LLC
115 MWIn study Cumberland, VAPJM Jan 2025target 2026
Gas project CLPT G30, Laramie County
Gas · Black Hills Electric Generation, LLC
115 MWIn study Laramie, WYWest May 2024target 2029
Gas project 40969, Laramie County
Gas · Cheyenne Light, Fuel and Power Company
115 MWIn study Laramie, WYWest Aug 2025target 2028
Solar + storage project J2886, Sangamon County
Solar + storage
115 MWIn study Sangamon, ILMISO Sep 2022target 2026
Battery storage project 563648, Gaston County
Battery storage
115 MWIn study Gaston, NCSoutheast Jun 2022target 2027
Battery storage project AH2-332, Prince George's County
Battery storage
115 MWIn study Prince George's, MDPJM Mar 2022target 2025
Solar project J4142, Franklin Parish County
Solar
115 MWIn study Franklin Parish, LAMISO Oct 2025target 2030
Gas project CLPT G31, Laramie County
Gas · Cheyenne Light, Fuel & Power
115 MWIn study Laramie, WYWest May 2024target 2029
Solar + storage project J4139, Nevada County
Solar + storage
115 MWIn study Nevada, ARMISO Sep 2025target 2030
Solar project AH2-264, Van Wert County
Solar
115 MWIn study Van Wert, OHPJM Mar 2022target 2026
Battery storage project 956294, Rockingham County
Battery storage
115 MWIn study Rockingham, NCSoutheast Jun 2024
Hayrick BESS
Battery storage · Gransolar Texas Five LLC
114 MWIn study Coke, TXERCOT Aug 2022target 2028
Neptune Gas Generation Plant
Gas · BPX Production Company
114 MWIn study Reeves, TXERCOT Dec 2024target 2028
Solar project GEN-2022-104, Bryan County
Solar
113 MWIn study Bryan, OKSPP Jan 2023target 2028
Lost Pines Gas Recip Phase 2
Gas · LCRA
113 MWIn study Bastrop, TXERCOT Jul 2025target 2031
Solar project J3687, Fayette County
Solar
113 MWIn study Fayette, ILMISO Apr 2024target 2027
Angus Solar
Solar · Angus Solar, LLC
113 MWPaused / redesign Bosque, TXERCOT Nov 2017target 2026
Schneider Gas Rice
Gas · LCRA
113 MWIn study Caldwell, TXERCOT Jul 2025target 2029
Page 86 of 138

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines · Planned power plants (EIA)