Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.
Map
Requests
| Project | Capacity | Status |
|---|---|---|
| Denali Energy Storage Battery storage |
102 MW | Agreement signed |
| Blue Sky Sol Solar + storage ยท Blue Sky Solar LLC |
101 MW | Agreement signed |
| Matagorda Solar Solar ยท Matagorda Solar Farm, LLC |
101 MW | Agreement signed |
| Inertia BESS 2 Battery storage |
101 MW | Paused / redesign |
| BRP Diran BESS Battery storage ยท BRP Diran BESS LLC |
101 MW | Agreement signed |
| BRP Musca BESS Battery storage ยท BRP Musca BESS LLC |
101 MW | In study |
| Flat Creek Solar Solar ยท Flat Creek Solar NY LLC |
100 MW | In study |
| Onshore wind project G0635, Benton County Onshore wind |
100 MW | In study |
| Solar + storage project J1599, Iberia Parish County Solar + storage |
100 MW | In study |
| Onshore wind project J1725, Tazewell County Onshore wind |
100 MW | In study |
| Solar project J1610, Sangamon County Solar |
100 MW | In study |
| Butterfly Meadows Battery storage ยท Butterfly Meadows Solar Project, LLC |
100 MW | In study |
| Keyhole Wind Onshore wind |
100 MW | Agreement signed |
| Solar project J1778, Kenosha County Solar |
100 MW | Agreement signed |
| Flatrock Creek Solar II Solar |
100 MW | Agreement signed |
| Swift Creek Solar Solar + storage |
100 MW | Agreement signed |
| Battery storage project 86, Whatcom County Battery storage |
100 MW | Agreement signed |
| Solar project J1745, Winnebago County Solar |
100 MW | Agreement signed |
| Solar project 20-02261, Larimer County Solar |
100 MW | In study |
| Battery storage project J1845, Calhoun County Battery storage |
100 MW | In study |
| Prairie Creek Wind Phase 2 Onshore wind ยท Prairie Creek Wind Farm II, LLC |
100 MW | Agreement signed |
| Battery storage project Q358, Maricopa County Battery storage |
100 MW | Agreement signed |
| Battery storage project J1659, Washtenaw County Battery storage |
100 MW | Under construction |
| Solar project J1820, Lee County Solar |
100 MW | In study |
| Sanborn Hybrid 4 Solar + storage |
100 MW | Agreement signed |
| Flatrock Creek Solar I Solar |
100 MW | Agreement signed |
| Solar project J1777, Perry County Solar |
100 MW | In study |
| Solar project J1587, Muskegon County Solar |
100 MW | Agreement signed |
| Solar project GI-93, Macon County Solar |
100 MW | Agreement signed |
| Steward Creek Solar Solar ยท Steward Creek Solar, LLC |
100 MW | In study |
| Solar project GEN-2020-078, Washington County Solar |
100 MW | Agreement signed |
| SPC Bloom BESS Battery storage ยท BRP Blue Topaz 2, LLC |
100 MW | In study |
| Solar project J1748, Desoto County Solar |
100 MW | Agreement signed |
| Tillman Solar Park Solar |
100 MW | Agreement signed |
| Zinnia Storage Battery storage |
100 MW | Agreement signed |
| Solar project GEN-2020-092, Mayes County Solar |
100 MW | In study |
| Nicholas Solar Solar |
100 MW | Agreement signed |
| Solar project J1577, Grant County Solar |
100 MW | In study |
| Battery storage project GEN-2021-001, Bryan County Battery storage |
100 MW | Agreement signed |
| Solar + storage project IA-PNM-2020-07, San Juan County Solar + storage |
100 MW | In study |
| Solar + storage project 137, Orangeburg County Solar + storage |
100 MW | Under construction |
| New Haven Solar Solar |
100 MW | Agreement signed |
| Battery storage project 81, Pierce County Battery storage |
100 MW | Paused / redesign |
| Solar project J1564, Washington Parish County Solar |
100 MW | Agreement signed |
| Solar project J1657, St. Croix County Solar |
100 MW | In study |
| Solar project J1612, Union County Solar |
100 MW | In study |
| Solar project J1706, Green County Solar |
100 MW | Agreement signed |
| Solar project J1714, Fayette County Solar |
100 MW | In study |
| Solar project GI-90, Randolph County Solar |
100 MW | Agreement signed |
| Remington BESS Battery storage |
100 MW | Agreement signed |
Capacity in the queue by state
Click a state to drill down.
By grid region
ISO/RTO markets and the non-ISO West and Southeast.
- ERCOT (Texas)108 ยท 26.4 GW
- West (non-ISO utilities)100 ยท 24.5 GW
- PJM (Mid-Atlantic, Midwest)178 ยท 16.6 GW
- CAISO (California)41 ยท 16.3 GW
- MISO (Midcontinent)95 ยท 15.7 GW
- SPP (Southwest Power Pool)35 ยท 8,165 MW
- Southeast (non-ISO utilities)55 ยท 7,020 MW
- NYISO (New York)19 ยท 2,230 MW
- ISO-NE (New England)4 ยท 129 MW
Requests by year joined
Capacity of requests in this view, by the year they entered the queue. Click a year.
Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines ยท Planned power plants (EIA)