United States βΊ Grid βΊ Interconnection queues βΊ Texas
BATTERY STORAGE Β· ERCOTInertia BESS 2
Inertia BESS 2 is a 101 MW battery storage request suspended in the ERCOT interconnection queue, in Haskell County, Texas.
Queue statusPaused / redesign
- PlanningQueued Oct 2020 (current stage)
- Consented (not yet reached)
- Construction (not yet reached)
- Operating (not yet reached)
- Closed (not yet reached)
Studies assess what grid upgrades the project would need and who pays for them. A signed interconnection agreement is the main step before construction.
Request details
- Queue ID
- 22INR0375
- Grid region
- ERCOT (Texas)
- Location
- Haskell County, Texas
- Technology
- Battery: 101 MW
- Total requested
- 101 MW
- Queue status
- Suspended
- Entered queue
- 12 October 2020
Location
Marker shows the centre of Haskell County; the queue data does not give exact sites.
Other requests in Haskell County
- Briggs StorageSolar + storage Β· 336 MW Β· agreement signed
- Briggs SolarSolar + storage Β· 324 MW Β· agreement signed
- Quantum StorageSolar + storage Β· 322 MW Β· agreement signed
- Solace StorageSolar + storage Β· 322 MW Β· agreement signed
- Quantum SolarSolar + storage Β· 322 MW Β· agreement signed
- Solace SolarSolar + storage Β· 322 MW Β· agreement signed
- Rubicon Alpha WindOnshore wind Β· 226 MW Β· agreement signed
- Inertia SolarSolar Β· 202 MW Β· agreement signed
- Millers Branch Solar ISolar Β· 200 MW Β· agreement signed
- Millers Branch Solar IISolar Β· 178 MW Β· agreement signed
- Millers Branch Solar IIISolar Β· 133 MW Β· agreement signed
- Grasshopper SolarSolar Β· 408 MW Β· in study
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem