United States โบ Grid โบ Interconnection queues
OCTARY USA ยท INTERCONNECTION QUEUESWithdrawn queue requests in the USA (2021 requests) โ page 8
Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.
Map
Requests
| Project | Capacity | Status |
|---|---|---|
| Solar project J1857, Cross County Solar |
250 MW | Withdrawn / abandoned |
| Solar + storage project C1-52, Tooele County Solar + storage |
250 MW | Withdrawn / abandoned |
| Solar + storage project GI-2021-12, Pueblo County Solar + storage |
250 MW | Withdrawn / abandoned |
| Onshore wind project GEN-2021-037, Perkins County Onshore wind |
244 MW | Withdrawn / abandoned |
| Storage Battery storage |
242 MW | Withdrawn / abandoned |
| Otros Alamitos Energy Storage Battery storage |
242 MW | Withdrawn / abandoned |
| Battery storage project AH1-256, Grant County Battery storage |
240 MW | Withdrawn / abandoned |
| Solar project GEN-2021-055, Titus County Solar |
240 MW | Withdrawn / abandoned |
| Solar project GEN-2021-073, Lancaster County Solar |
240 MW | Withdrawn / abandoned |
| Mount Storm Repower BESS 1 Battery storage ยท Mount Storm BESS 1 LLC |
240 MW | Withdrawn / abandoned |
| Cannae Solar + storage |
234 MW | Withdrawn / abandoned |
| Solitude Hybrid Solar + storage |
232 MW | Withdrawn / abandoned |
| Amber Solar and Storage Solar + storage ยท Hanwha Q CELLS USA |
232 MW | Withdrawn / abandoned |
| Blue Bird Solar + storage |
232 MW | Withdrawn / abandoned |
| Solar project AH1-624, Clearfield County Solar |
230 MW | Withdrawn / abandoned |
| Lacuna Energy Storage Battery storage |
227 MW | Withdrawn / abandoned |
| Flyway Solar Solar + storage |
227 MW | Withdrawn / abandoned |
| Battery storage project AH1-602, Lee County Battery storage |
225 MW | Withdrawn / abandoned |
| Solar + storage project J2076, San Jacinto County Solar + storage |
225 MW | Withdrawn / abandoned |
| Hi225SB Project Solar + storage |
225 MW | Withdrawn / abandoned |
| Battery storage project GEN-2021-009, Beadle County Battery storage |
225 MW | Withdrawn / abandoned |
| Battery storage project Q412, Maricopa County Battery storage |
225 MW | Withdrawn / abandoned |
| Stoneman Battery storage |
225 MW | Withdrawn / abandoned |
| Solar + storage project Q413, Pinal County Solar + storage |
223 MW | Withdrawn / abandoned |
| Solar project IA-PNM-2021-22, Bernalillo County Solar |
220 MW | Withdrawn / abandoned |
| Rangeland Solar Solar + storage |
217 MW | Withdrawn / abandoned |
| Myrtle Solar + storage |
216 MW | Withdrawn / abandoned |
| Solar project AG2-687, Garrard County Solar |
215 MW | Withdrawn / abandoned |
| Solar project AG2-686, Nicholas County Solar |
215 MW | Withdrawn / abandoned |
| Other project G2021-01, Pierce County Other |
215 MW | Withdrawn / abandoned |
| Neal Solar II Solar ยท Neal Solar, LLC |
214 MW | Withdrawn / abandoned |
| Sunridge Storage Battery storage |
214 MW | Withdrawn / abandoned |
| Goldenstar Energy Storage Battery storage |
214 MW | Withdrawn / abandoned |
| Timber Energy Storage Battery storage |
214 MW | Withdrawn / abandoned |
| Blitz Energy Storage Battery storage |
214 MW | Withdrawn / abandoned |
| Stageline Energy Storage Battery storage |
214 MW | Withdrawn / abandoned |
| Flea Flicker Energy Storage Battery storage |
214 MW | Withdrawn / abandoned |
| Brix Energy Storage Battery storage |
214 MW | Withdrawn / abandoned |
| Kratos BESS Battery storage |
214 MW | Withdrawn / abandoned |
| Toledo Storage Battery storage |
213 MW | Withdrawn / abandoned |
| Solar project GI-2021-13, Pueblo County Solar |
213 MW | Withdrawn / abandoned |
| Onshore wind project AG2-674, Whiteside County Onshore wind |
212 MW | Withdrawn / abandoned |
| Battery storage project J2095, Tama County Battery storage |
212 MW | Withdrawn / abandoned |
| Northline Solar + storage |
212 MW | Withdrawn / abandoned |
| Solar project J1737, Rush County Solar |
210 MW | Withdrawn / abandoned |
| Solar project IC-944, Turner County Solar |
210 MW | Withdrawn / abandoned |
| Peeler Solar Solar ยท Peeler Solar, LLC |
210 MW | Withdrawn / abandoned |
| Solar project GEN-2021-010, Beckham County Solar |
208 MW | Withdrawn / abandoned |
| Solar project GEN-2021-014, Beckham County Solar |
208 MW | Withdrawn / abandoned |
| Marley Battery storage |
206 MW | Withdrawn / abandoned |
Capacity in the queue by state
Click a state to drill down.
By grid region
ISO/RTO markets and the non-ISO West and Southeast.
- CAISO (California)220 ยท 82.8 GW
- West (non-ISO utilities)339 ยท 78.3 GW
- PJM (Mid-Atlantic, Midwest)819 ยท 65.0 GW
- MISO (Midcontinent)267 ยท 38.5 GW
- NYISO (New York)149 ยท 23.5 GW
- Southeast (non-ISO utilities)123 ยท 16.3 GW
- ERCOT (Texas)77 ยท 13.4 GW
- SPP (Southwest Power Pool)70 ยท 13.1 GW
- ISO-NE (New England)85 ยท 8,317 MW
Requests by year joined
Capacity of requests in this view, by the year they entered the queue. Click a year.
Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines ยท Planned power plants (EIA)