Toledo Storage

Toledo Storage is a 213 MW battery storage request withdrawn in the CAISO interconnection queue, in Contra Costa County, California, connecting to PGAE.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Apr 2021 (completed)
  2. Withdrawn / abandonedDec 2022 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
1902
Grid region
CAISO (California)
Utility / transmission owner
PGAE
Connection point (POI)
Contra Costa Substation 230 kV
Location
Contra Costa County, California
Technology
Battery: 213 MW
Total requested
213 MW
Service type
Network resource (NRIS)
Study phase
System Impact Study
Queue status
Withdrawn
Entered queue
15 April 2021
Proposed online date
October 2025
Withdrawn
December 2022

Location

Marker shows the centre of Contra Costa County; the queue data does not give exact sites.