United States β€Ί Grid β€Ί Interconnection queues β€Ί New Mexico

SOLAR Β· WEST

Solar project IA-PNM-2021-22, Bernalillo County

Solar project IA-PNM-2021-22, Bernalillo County is a 220 MW solar request withdrawn in the West interconnection queue, in Bernalillo County, New Mexico, connecting to Public Service Company of New Mexico.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Nov 2021 (completed)
  2. Withdrawn / abandonedFeb 2021 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
IA-PNM-2021-22
Grid region
West (non-ISO utilities)
Utility / transmission owner
Public Service Company of New Mexico
Connection point (POI)
Diamond Tail Switching Station
Location
Bernalillo County, New Mexico
Technology
Solar: 220 MW
Total requested
220 MW
Service type
Network resource (NRIS)
Queue status
Withdrawn
Entered queue
5 November 2021
Proposed online date
June 2024
Withdrawn
February 2021

Location

Marker shows the centre of Bernalillo County; the queue data does not give exact sites.

Power plants in New Mexico Β· Transmission lines in New Mexico

Other requests in Bernalillo County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem