United States βΊ Grid βΊ Interconnection queues βΊ West Virginia
SOLAR Β· PJMSolar project AG2-686, Nicholas County
Solar project AG2-686, Nicholas County is a 215 MW solar request withdrawn in the PJM interconnection queue, in Nicholas County, West Virginia, connecting to APS.
Queue statusWithdrawn / abandoned
- PlanningQueued Mar 2021 (completed)
- Withdrawn / abandonedDec 2024 (project stopped here)
- Consented (not reached)
- Construction (not reached)
- Operating (not reached)
- Closed (not reached)
Request details
- Queue ID
- AG2-686
- Grid region
- PJM (Mid-Atlantic, Midwest)
- Utility / transmission owner
- APS
- Connection point (POI)
- Powell Mountain 138 kV
- Location
- Nicholas County, West Virginia
- Technology
- Solar: 215 MW
- Total requested
- 215 MW
- Service type
- Network resource (NRIS)
- Study phase
- Feasibility Study
- Queue status
- Withdrawn
- Entered queue
- 31 March 2021
- Proposed online date
- June 2024
- Withdrawn
- December 2024
Location
Marker shows the centre of Nicholas County; the queue data does not give exact sites.
Power plants in West Virginia Β· Transmission lines in West Virginia
Other requests in Nicholas County
- Deep Lake SolarSolar Β· 150 MW Β· agreement signed
- Nicholas SolarSolar Β· 100 MW Β· agreement signed
- Solar project AI2-332, Nicholas CountySolar Β· 40.0 MW Β· in study
- Solar project AI2-339, Nicholas CountySolar Β· 26.8 MW Β· in study
- Battery storage project AG2-314, Nicholas CountyBattery storage Β· 67.0 MW Β· withdrawn
- Battery storage project AH1-426A, Nicholas CountyBattery storage Β· 32.3 MW Β· withdrawn
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem