BATTERY STORAGE · PJM

Mount Storm Repower BESS 1

Mount Storm Repower BESS 1 is a 240 MW battery storage request withdrawn in the PJM interconnection queue, in Grant County, West Virginia, connecting to APS.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Sep 2021 (completed)
  2. Withdrawn / abandonedJul 2025 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
AH1-255
Grid region
PJM (Mid-Atlantic, Midwest)
Utility / transmission owner
APS
Developer
Mount Storm BESS 1 LLC
Connection point (POI)
Greenland Gap III
Location
Grant County, West Virginia
Technology
Battery: 240 MW
Total requested
240 MW
Service type
Network resource (NRIS)
Study phase
In Progress (unknown study)
Queue status
Withdrawn
Entered queue
9 September 2021
Proposed online date
July 2025
Withdrawn
July 2025

Location

Marker shows the centre of Grant County; the queue data does not give exact sites.

Power plants in West Virginia · Transmission lines in West Virginia

Other requests in Grant County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem