SOLAR + STORAGE Β· CAISO

Northline

Northline is a 212 MW solar + storage request withdrawn in the CAISO interconnection queue, in Merced County, California, connecting to PGAE.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Apr 2021 (completed)
  2. Withdrawn / abandonedNov 2022 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
1942
Grid region
CAISO (California)
Utility / transmission owner
PGAE
Connection point (POI)
Los Banos-Livingston-Canal 70 kV Line
Location
Merced County, California
Technology
Solar: 106 MW Β· Battery: 106 MW
Total requested
212 MW
Service type
Network resource (NRIS)
Study phase
Feasibility Study
Queue status
Withdrawn
Entered queue
15 April 2021
Proposed online date
June 2024
Withdrawn
November 2022

Location

Marker shows the centre of Merced County; the queue data does not give exact sites.