🔌 EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more → Skip to main content

United States › Grid › Interconnection queues › California

BATTERY STORAGE · CAISO

Stoneman

Stoneman is a 225 MW battery storage request withdrawn in the CAISO interconnection queue, in Contra Costa County, California, connecting to PGAE.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Apr 2021 (completed)
  2. Withdrawn / abandonedDec 2022 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
1899
Grid region
CAISO (California)
Utility / transmission owner
PGAE
Connection point (POI)
Pittsburg Substation 230 kV
Location
Contra Costa County, California
Technology
Battery: 225 MW
Total requested
225 MW
Service type
Network resource (NRIS)
Study phase
System Impact Study
Queue status
Withdrawn
Entered queue
15 April 2021
Proposed online date
November 2024
Withdrawn
December 2022

Location

Marker shows the centre of Contra Costa County; the queue data does not give exact sites.

Power plants in California · Transmission lines in California

Other requests in Contra Costa County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem