🔌 EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more → Skip to main content

United States › Grid › Interconnection queues

OCTARY USA · INTERCONNECTION QUEUES

Interconnection queue in the USA (2025 requests) — page 7

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown1,836452.0 GW
Active in queue452.0 GW1,836 requests
Agreement signed4,701 MW27 requests
Withdrawn47497.1 GW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

1,836 requests · page 7 of 37
ProjectCapacityStatusLocationRegionQueuedOnline
Solar + storage project ERAS-2025-015, Finney County
Solar + storage
400 MWIn study Finney, KSSPP Sep 2025target 2029
Solar project GI-2025-09, Cheyenne County
Solar
400 MWIn study Cheyenne, COWest Apr 2025target 2029
Solar + storage project S1125, St. Francis County
Solar + storage
400 MWIn study St. Francis, ARMISO Oct 2025target 2028
Solar + storage project T2-076, Utah County
Solar + storage
400 MWIn study Utah, UTWest Sep 2025target 2027
Battery storage project T2-083, Emery County
Battery storage
400 MWIn study Emery, UTWest Sep 2025target 2030
Solar + storage project GI-2025-08, El Paso County
Solar + storage
400 MWIn study El Paso, COWest Apr 2025target 2029
Onshore wind project IA-PNM-2025-19, Torrance County
Onshore wind
400 MWIn study Torrance, NMWest Mar 2025target 2028
Battery storage project AG2-545, Mchenry County
Battery storage · Monarch Grid, LLC
400 MWIn study Mchenry, ILPJM Mar 2025target 2024
Solar project AG2-570, Brunswick County
Solar · Zeus Energy, LLC
400 MWIn study Brunswick, VAPJM Mar 2025target 2024
Va400B
Battery storage
400 MWIn study Dona Ana, NMWest Jun 2025target 2028
Solar + storage project T2-031, Morrow County
Solar + storage · PacifiCorp
400 MWIn study Morrow, ORWest Sep 2025target 2028
Solar + storage project T2-087, Morrow County
Solar + storage · PacifiCorp
400 MWIn study Morrow, ORWest Sep 2025target 2028
Solar + storage project T2-030, Morrow County
Solar + storage · PacifiCorp
400 MWIn study Morrow, ORWest Sep 2025target 2028
Solar + storage project T2-086, Morrow County
Solar + storage · PacifiCorp
400 MWIn study Morrow, ORWest Sep 2025target 2028
Solar + storage project T2-029, Bingham County
Solar + storage · PacifiCorp
398 MWIn study Bingham, IDWest Sep 2025target 2028
Faribault Energy Park
Gas · MMPA (Minnesota Municipal Power Agency)
394 MWIn study Rice, MNMISO Aug 2025target 2028
Solar project GEN-2024-268, Muskogee County
Solar
390 MWIn study Muskogee, OKSPP Mar 2025target 2030
Solar project J3939, Beauregard Parish County
Solar
386 MWIn study Beauregard Parish, LAMISO Apr 2025target 2030
Solar project ERAS-2025-028, Hockley County
Solar
384 MWIn study Hockley, TXSPP Oct 2025target 2030
Moon Chapel Wind
Onshore wind · Orsted Onshore Development North America, LLC
379 MWIn study Tom Green, TXERCOT Feb 2025target 2028
Point Coupee
Gas · Entergy Louisiana, LLC
377 MWIn study Pointe Coupee Parish, LAMISO Oct 2025target 2028
Solar + storage project CS25-09, Adams County
Solar + storage
375 MWIn study Adams, WAWest Apr 2025target 2030
Solar + storage project IA-PNM-2025-01, Valencia County
Solar + storage
371 MWIn study Valencia, NMWest Jan 2025target 2030
Kilby1 Part 1 Small Block Simple Cycle
Gas · Energy Forge One LLC
371 MWIn study Reeves, TXERCOT Oct 2025target 2027
Viento Bravo Wind
Onshore wind · Webb Wind, LLC
367 MWIn study Jim Hogg, TXERCOT Oct 2025target 2028
Solar project J3942, Vigo County
Solar
365 MWIn study Vigo, INMISO Feb 2025target 2030
Gas project T2-020, Juab County
Gas · PacifiCorp
363 MWIn study Juab, UTWest Sep 2025target 2029
Battery storage project J3994, Monroe County
Battery storage
360 MWIn study Monroe, MIMISO Apr 2025target 2028
Solar + storage project GI-2025-07, Morgan County
Solar + storage
360 MWIn study Morgan, COWest Apr 2025target 2029
Onshore wind project E0015, Franklin County
Onshore wind · Interstate Power and Light Company (IPL)
360 MWIn study Franklin, IAMISO Aug 2025target 2028
Gas project GEN-2024-213, Cass County
Gas
360 MWIn study Cass, NESPP Mar 2025target 2035
Solar + storage project G1086, Columbia County
Solar + storage
359 MWIn study Columbia, WAWest Aug 2025target 2029
Wildflower Storage
Battery storage · Wildflower Storage LLC
359 MWIn study Navarro, TXERCOT Jun 2025target 2028
Green Ocelot Solar
Solar + storage · Ocelot Solar LLC
357 MWIn study Kenedy, TXERCOT Jan 2025target 2028
Gas project GEN-2024-323, Choctaw County
Gas
357 MWIn study Choctaw, OKSPP Mar 2025target 2029
Solar + storage project GI-2025-12, Adams County
Solar + storage
355 MWIn study Adams, COWest May 2025target 2029
Max 4 Wind
Onshore wind · Lake Creek Wind, LLC
353 MWIn study Haskell, TXERCOT Jul 2025target 2028
Longview Wind
Onshore wind · Longview Wind, LLC
353 MWAgreement signed Dawson, TXERCOT Sep 2025target 2028
Battery storage project Q2516, Pinal County
Battery storage
352 MWIn study Pinal, AZWest Feb 2025target 2028
Brookesmith Storage
Battery storage · Brookesmith Storage LLC
351 MWIn study Brown, TXERCOT Apr 2025target 2029
Solar + storage project ERAS-2025-030, Chaves County
Solar + storage
350 MWIn study Chaves, NMSPP Oct 2025target 2030
Other project Q606, Maricopa County
Other
350 MWIn study Maricopa, AZWest May 2025target 2030
Solar project GEN-2024-289, Henry County
Solar
350 MWIn study Henry, MOSPP Mar 2025target 2029
Battery storage project Q584, Pinal County
Battery storage
350 MWIn study Pinal, AZWest May 2025target 2029
Solar + storage project GEN-2024-280, Andrews County
Solar + storage
350 MWIn study Andrews, TXSPP Mar 2025target 2029
Battery storage project J3872, Wayne County
Battery storage
350 MWIn study Wayne, MIMISO Jan 2025target 2029
Onshore wind project J4203, Huron County
Onshore wind
350 MWIn study Huron, MIMISO Jun 2025target 2028
Solar project J3889, Union County
Solar
350 MWIn study Union, ARMISO Feb 2025target 2030
Solar project GEN-2024-338, Johnston County
Solar
350 MWIn study Johnston, OKSPP Mar 2025target 2030
Solar project AG2-436, Sussex County
Solar · Monarch Solar, LLC
350 MWIn study Sussex, VAPJM Apr 2025target 2023
Page 7 of 37

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines · Planned power plants (EIA)