Battery storage project J3994, Monroe County

Battery storage project J3994, Monroe County is a 360 MW battery storage request in interconnection study in the MISO interconnection queue, in Monroe County, Michigan, connecting to METC.

Queue statusIn planning
  1. PlanningQueued Apr 2025 (current stage)
  2. Consented (not yet reached)
  3. Construction (not yet reached)
  4. OperatingTarget Apr 2028 (not yet reached)
  5. Closed (not yet reached)

Studies assess what grid upgrades the project would need and who pays for them. A signed interconnection agreement is the main step before construction.

Request details

Queue ID
J3994
Grid region
MISO (Midcontinent)
Utility / transmission owner
METC
Connection point (POI)
18MOROCCO 256583
Location
Monroe County, Michigan
Technology
Battery: 360 MW
Total requested
360 MW
Service type
Network resource (NRIS)
Queue status
Active
Entered queue
17 April 2025
Proposed online date
April 2028

Location

Marker shows the centre of Monroe County; the queue data does not give exact sites.