Point Coupee is a 377 MW gas request in interconnection study in the MISO interconnection queue, in Pointe Coupee Parish County, Louisiana, connecting to Entergy Louisiana, LLC.
Queue statusIn planning
- PlanningQueued Oct 2025 (current stage)
- Consented (not yet reached)
- Construction (not yet reached)
- OperatingTarget Oct 2028 (not yet reached)
- Closed (not yet reached)
Studies assess what grid upgrades the project would need and who pays for them. A signed interconnection agreement is the main step before construction.
Request details
- Queue ID
- E0051
- Grid region
- MISO (Midcontinent)
- Utility / transmission owner
- Entergy Louisiana, LLC
- Developer
- Entergy Louisiana, LLC
- Connection point (POI)
- Big Cajun 500kv
- Location
- Pointe Coupee Parish County, Louisiana
- Technology
- Gas: 377 MW
- Total requested
- 377 MW
- Service type
- Network resource (NRIS)
- Study phase
- Request Status: Active; Post GIA Status: Not started
- Queue status
- Active
- Entered queue
- 23 October 2025
- Proposed online date
- October 2028
Location
Marker shows the centre of Pointe Coupee Parish County; the queue data does not give exact sites.
Other requests in Pointe Coupee Parish County
- Solar project J1465, Pointe Coupee Parish CountySolar · 150 MW · agreement signed
- Solar project J1368, Pointe Coupee Parish CountySolar · 200 MW · built
- Solar project J1372, Pointe Coupee Parish CountySolar · 100 MW · built
- Gas project E002, Pointe Coupee Parish CountyGas · 15.0 MW · built
- Solar project J2183, Pointe Coupee Parish CountySolar · 200 MW · withdrawn
- Solar project J3822, Pointe Coupee Parish CountySolar · 140 MW · withdrawn
- Solar project J3083, Pointe Coupee Parish CountySolar · 100 MW · withdrawn
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem