SOLAR Β· MISO

Solar project J3822, Pointe Coupee Parish County

Solar project J3822, Pointe Coupee Parish County is a 140 MW solar request withdrawn in the MISO interconnection queue, in Pointe Coupee Parish County, Louisiana, connecting to ENTERGY LOUISIANA.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Apr 2024 (completed)
  2. Withdrawn / abandonedDec 2025 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
J3822
Grid region
MISO (Midcontinent)
Utility / transmission owner
ENTERGY LOUISIANA
Connection point (POI)
DEVIN - LIVONIA 138.0kV
Location
Pointe Coupee Parish County, Louisiana
Technology
Solar: 140 MW
Total requested
140 MW
Service type
Network resource (NRIS)
Study phase
Study Phase: DPP 1
Queue status
Withdrawn
Entered queue
18 April 2024
Proposed online date
January 2028
Withdrawn
December 2025

Location

Marker shows the centre of Pointe Coupee Parish County; the queue data does not give exact sites.

Power plants in Louisiana Β· Transmission lines in Louisiana

Other requests in Pointe Coupee Parish County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem