United States › Grid › Interconnection queues › Louisiana

SOLAR · MISO

Solar project J1372, Pointe Coupee Parish County

Solar project J1372, Pointe Coupee Parish County is a 100 MW solar request built and operating in the MISO interconnection queue, in Pointe Coupee Parish County, Louisiana, connecting to ENTERGY LOUISIANA.

Queue statusOperating
  1. PlanningQueued Apr 2019 (completed)
  2. ConsentedNov 2021 (completed)
  3. Construction (completed)
  4. OperatingJun 2023 (current stage)
  5. Closed (not yet reached)

Request details

Queue ID
J1372
Grid region
MISO (Midcontinent)
Utility / transmission owner
ENTERGY LOUISIANA
Connection point (POI)
Fancy Point - Waterloo 230 kV Line (J1368 POI)
Location
Pointe Coupee Parish County, Louisiana
Technology
Solar: 100 MW
Total requested
100 MW
Service type
Network resource (NRIS)
Study phase
Study Phase: GIA Complete; Post GIA Status: In Service
Queue status
Operational
Entered queue
29 April 2019
Agreement signed
30 November 2021
Proposed online date
June 2023
Came online
June 2023

Location

Marker shows the centre of Pointe Coupee Parish County; the queue data does not give exact sites.

Power plants in Louisiana · Transmission lines in Louisiana

Other requests in Pointe Coupee Parish County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem