United States › Grid › Interconnection queues › Louisiana
SOLAR · MISOSolar project J1372, Pointe Coupee Parish County
Solar project J1372, Pointe Coupee Parish County is a 100 MW solar request built and operating in the MISO interconnection queue, in Pointe Coupee Parish County, Louisiana, connecting to ENTERGY LOUISIANA.
Request details
- Queue ID
- J1372
- Grid region
- MISO (Midcontinent)
- Utility / transmission owner
- ENTERGY LOUISIANA
- Connection point (POI)
- Fancy Point - Waterloo 230 kV Line (J1368 POI)
- Location
- Pointe Coupee Parish County, Louisiana
- Technology
- Solar: 100 MW
- Total requested
- 100 MW
- Service type
- Network resource (NRIS)
- Study phase
- Study Phase: GIA Complete; Post GIA Status: In Service
- Queue status
- Operational
- Entered queue
- 29 April 2019
- Agreement signed
- 30 November 2021
- Proposed online date
- June 2023
- Came online
- June 2023
Location
Marker shows the centre of Pointe Coupee Parish County; the queue data does not give exact sites.
Other requests in Pointe Coupee Parish County
- Solar project J1465, Pointe Coupee Parish CountySolar · 150 MW · agreement signed
- Point CoupeeGas · 377 MW · in study
- Solar project J1368, Pointe Coupee Parish CountySolar · 200 MW · built
- Gas project E002, Pointe Coupee Parish CountyGas · 15.0 MW · built
- Solar project J2183, Pointe Coupee Parish CountySolar · 200 MW · withdrawn
- Solar project J3822, Pointe Coupee Parish CountySolar · 140 MW · withdrawn
- Solar project J3083, Pointe Coupee Parish CountySolar · 100 MW · withdrawn
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem