United States › Grid › Interconnection queues › Texas

OCTARY USA · INTERCONNECTION QUEUES

Interconnection queue in Texas (2023 requests) — page 7

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown36979.0 GW
Active in queue79.0 GW369 requests
Agreement signed25.0 GW108 requests
Withdrawn11324.2 GW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

369 requests · page 7 of 8
ProjectCapacityStatusLocationRegionQueuedOnline
Lemma Solar
Solar · Greening USA Corp.
101 MWIn study Knox, TXERCOT Apr 2023target 2028
Felix Storage
Solar + storage · Felix 1, LLC
101 MWIn study Wilbarger, TXERCOT Jan 2023target 2027
Timber Cove Solar SLF
Solar + storage · Freestone Solar, LLC
101 MWIn study Freestone, TXERCOT May 2023target 2027
Mud Cat Solar SLF
Solar + storage · Mud Cat Solar, LLC
101 MWIn study Lamar, TXERCOT Oct 2023target 2027
Timberline Storage
Solar + storage · Timberline Renewables, LLC
101 MWIn study Nacogdoches, TXERCOT Aug 2023target 2029
Wizard Ranch Solar
Solar
101 MWPaused / redesign Jack, TXERCOT May 2023
Lazy Frog Solar SLF
Solar + storage · Lazy Frog Solar, LLC
100 MWIn study Franklin, TXERCOT Sep 2023target 2028
Goldfinch Storage
Solar + storage · BT DJ4M Solar, LLC
100 MWIn study Van Zandt, TXERCOT Oct 2023target 2028
Firebird Solar
Solar
100 MWPaused / redesign Ector, TXERCOT Nov 2023target 2026
Pledgor BESS
Battery storage · Pledgor BESS
100 MWIn study Matagorda, TXERCOT May 2023target 2028
Rogers Creek BESS
Battery storage · Dialville BESS
100 MWIn study Cherokee, TXERCOT May 2023target 2028
Blue Summit Energy Storage
Wind + storage · NextEra Energy Interconnection Holdings, LLC
100 MWAgreement signed Wilbarger, TXERCOT Oct 2023target 2026
IEP Blackhawk
Battery storage · IEP Texas Verde II, llc
100 MWIn study Galveston, TXERCOT Apr 2023target 2026
Visol 1 Solar
Solar · VISOL 1 SOLAR, LLC
94.8 MWIn study Val Verde, TXERCOT Oct 2023target 2028
Trinity Hills BESS SLF
Battery storage · Phoenix Battery Storage, LLC
94.0 MWIn study Archer, TXERCOT Nov 2023target 2027
Solar project GEN-2023-241, Franklin County
Solar
93.0 MWIn study Franklin, TXSPP Oct 2023target 2029
HappyDogSolar
Solar + storage · Rosula Solar LLC
85.5 MWAgreement signed Milam, TXERCOT Jun 2023target 2027
RedSun BESS
Solar + storage · Gransolar Texas Twenty Two
84.0 MWIn study Burnet, TXERCOT Dec 2023target 2027
FLIFER Solar I
Solar · FLIFER LLC
84.0 MWIn study Ward, TXERCOT Mar 2023target 2027
RedSun Solar
Solar + storage · Gransolar Texas Twenty Two
82.6 MWAgreement signed Burnet, TXERCOT Dec 2023target 2027
Proving Ground Solar
Solar + storage · Lantana Solar LLC
82.1 MWIn study Schleicher, TXERCOT Jul 2023target 2028
Stegall Solar
Solar + storage · BT Martin Solar, LLC
81.6 MWIn study Robertson, TXERCOT Aug 2023target 2027
Flying Kite Solar
Solar + storage · FLYING KITE SOLAR LLC
80.4 MWAgreement signed Zavala, TXERCOT Apr 2023target 2027
Hinkell BESS
Battery storage · Reveille BESS
78.1 MWIn study La Salle, TXERCOT Aug 2023target 2027
Sherbino II BESS SLF
Battery storage · Phoenix Battery Storage, LLC
77.4 MWAgreement signed Pecos, TXERCOT Nov 2023target 2027
Cairos Storage
Solar + storage · Cairos Solar, LLC
77.3 MWIn study Kinney, TXERCOT Oct 2023target 2026
Dionysus Storage
Solar + storage · Dionysus Solar, LLC
77.3 MWIn study Houston, TXERCOT Jun 2023target 2027
Myers Storage
Solar + storage · BT Myers Solar, LLC
76.0 MWIn study Bee, TXERCOT Jun 2023target 2028
Proteus Vernon Solar SLF
Solar + storage · Vernon Solar and Storage LLC (a Delaware LLC)
75.0 MWIn study Wilbarger, TXERCOT Mar 2023target 2028
French Riviera Storage
Battery storage · Arana Creek Battery Storage LLC
75.0 MWIn study Kleberg, TXERCOT Feb 2023target 2028
Valdivian Solar
Solar · Abei Energy Green III LLC
74.9 MWIn study Hunt, TXERCOT Feb 2023target 2028
Pato Blanco Storage
Battery storage · TX BESS 4, LLC
71.3 MWIn study Fort Bend, TXERCOT May 2023target 2026
Edens Solar
Solar · Hill PV, LLC
70.4 MWIn study Hill, TXERCOT Oct 2023target 2027
Indigo Storage 4
Solar + storage · Innovative Solar 245, LLC
60.0 MWIn study Fisher, TXERCOT Oct 2023target 2026
Indigo Storage 2
Solar + storage · Innovative Solar 245, LLC
60.0 MWIn study Fisher, TXERCOT Sep 2023target 2026
Indigo Storage 3
Solar + storage · Innovative Solar 245, LLC
60.0 MWIn study Fisher, TXERCOT Nov 2023target 2026
Sol Marina Energy Center BESS
Solar + storage · Adapture Solar Development, LLC
57.2 MWAgreement signed Ellis, TXERCOT Oct 2023target 2027
Solar project GEN-2023-135, Bowie County
Solar
52.0 MWIn study Bowie, TXSPP Oct 2023target 2026
Orchard Ray BESS
Battery storage · Pettus BESS
51.9 MWIn study Bee, TXERCOT Jun 2023target 2027
Proving Ground BESS
Solar + storage · Lantana Solar LLC
51.4 MWIn study Schleicher, TXERCOT Jul 2023target 2028
Ayass BESS
Battery storage · Harvick BESS, LLC
51.3 MWIn study Throckmorton, TXERCOT Dec 2023target 2028
Black Bear BESS
Solar + storage · ESCONDIDO DRAW RESOURCES, LLC
51.2 MWIn study Crockett, TXERCOT Dec 2023target 2028
Lupinus Storage 3
Solar + storage · Lupinus Solar 2, LLC
50.9 MWAgreement signed Franklin, TXERCOT Sep 2023target 2026
Stegall Storage
Solar + storage · BT Martin Solar, LLC
50.5 MWIn study Robertson, TXERCOT Aug 2023target 2027
Surfside Energy Storage
Battery storage · Rocky Mountain Energy Holdings, LLC
50.3 MWIn study Brazoria, TXERCOT Jul 2023target 2028
Marick Rose BESS
Battery storage · Marick BESS
50.2 MWIn study Fort Bend, TXERCOT Jul 2023target 2026
Fort Chadbourne Cattle BESS
Battery storage · Fort Chadbourne BESS
50.2 MWIn study Coke, TXERCOT Aug 2023target 2027
Beeman BESS
Battery storage · Beeman BESS LLC
50.2 MWIn study Gonzales, TXERCOT Apr 2023target 2027
Battery storage project GEN-2023-SR9, Crosby County
Battery storage
50.0 MWAgreement signed Crosby, TXSPP Feb 2023target 2026
Old Sorrell Energy Storage
Battery storage
43.1 MWPaused / redesign Concho, TXERCOT Jun 2023

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines · Planned power plants (EIA)