United States › Grid › Interconnection queues › Texas
BATTERY STORAGE · ERCOTFrench Riviera Storage
French Riviera Storage is a 75.0 MW battery storage request in interconnection study in the ERCOT interconnection queue, in Kleberg County, Texas.
Queue statusIn planning
- PlanningQueued Feb 2023 (current stage)
- Consented (not yet reached)
- Construction (not yet reached)
- OperatingTarget May 2028 (not yet reached)
- Closed (not yet reached)
Studies assess what grid upgrades the project would need and who pays for them. A signed interconnection agreement is the main step before construction.
Request details
- Queue ID
- 24INR0516
- Grid region
- ERCOT (Texas)
- Developer
- Arana Creek Battery Storage LLC
- Connection point (POI)
- 5646 Riviera Substation 69kV
- Location
- Kleberg County, Texas
- Technology
- Battery: 75.0 MW
- Total requested
- 75.0 MW
- Study phase
- SS Completed, FIS Started, No IA
- Queue status
- Active
- Entered queue
- 9 February 2023
- Proposed online date
- May 2028
Location
Marker shows the centre of Kleberg County; the queue data does not give exact sites.
Other requests in Kleberg County
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem