πŸ”Œ EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more β†’ Skip to main content

United States β€Ί Grid β€Ί Interconnection queues β€Ί Texas

SOLAR Β· ERCOT

Bowhead Solar

Bowhead Solar is a 165 MW solar request withdrawn in the ERCOT interconnection queue, in Kleberg County, Texas.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Nov 2021 (completed)
  2. Withdrawn / abandonedApr 2025 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
24INR0132
Grid region
ERCOT (Texas)
Developer
Baffin Bay Solar, LLC
Connection point (POI)
Tap 138kV 8519 Kleberg β€šΓ„Γ¬ 8518 Kingsville
Location
Kleberg County, Texas
Technology
Solar: 165 MW
Total requested
165 MW
Study phase
FIS
Queue status
Withdrawn
Entered queue
15 November 2021
Proposed online date
January 2026
Withdrawn
April 2025

Location

Marker shows the centre of Kleberg County; the queue data does not give exact sites.

Power plants in Texas Β· Transmission lines in Texas

Other requests in Kleberg County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem