United States βΊ Grid βΊ Interconnection queues βΊ Texas
SOLAR Β· ERCOTEdens Solar
Edens Solar is a 70.4 MW solar request in interconnection study in the ERCOT interconnection queue, in Hill County, Texas.
Queue statusIn planning
- PlanningQueued Oct 2023 (current stage)
- Consented (not yet reached)
- Construction (not yet reached)
- OperatingTarget Aug 2027 (not yet reached)
- Closed (not yet reached)
Studies assess what grid upgrades the project would need and who pays for them. A signed interconnection agreement is the main step before construction.
Request details
- Queue ID
- 26INR0313
- Grid region
- ERCOT (Texas)
- Developer
- Hill PV, LLC
- Connection point (POI)
- Tap 69kV 3532 Itasca - 3523 Hillsboro
- Location
- Hill County, Texas
- Technology
- Solar: 70.4 MW
- Total requested
- 70.4 MW
- Study phase
- SS Completed, FIS Completed, No IA
- Queue status
- Active
- Entered queue
- 25 October 2023
- Proposed online date
- August 2027
Location
Marker shows the centre of Hill County; the queue data does not give exact sites.
Other requests in Hill County
- Compadre SolarSolar Β· 406 MW Β· agreement signed
- Blue Skies BESSBattery storage Β· 306 MW Β· agreement signed
- Aquilla Lake 3 WindOnshore wind Β· 297 MW Β· agreement signed
- OCI Cobb Creek SolarSolar + storage Β· 203 MW Β· agreement signed
- OCI Cobb Creek ESSSolar + storage Β· 202 MW Β· agreement signed
- Padrino SolarSolar Β· 201 MW Β· agreement signed
- High Noon SolarSolar + storage Β· 182 MW Β· agreement signed
- Vial BESSBattery storage Β· 135 MW Β· agreement signed
- Three W SolarSolar Β· 111 MW Β· agreement signed
- Midpoint SolarSolar Β· 98.3 MW Β· agreement signed
- High Noon StorageSolar + storage Β· 94.0 MW Β· agreement signed
- Payne BattlecreekSolar Β· 85.0 MW Β· agreement signed
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem