🔌 EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more → Skip to main content

United States › Grid › Interconnection queues

OCTARY USA · INTERCONNECTION QUEUES

Battery storage interconnection queue in the USA — page 6

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown2,226417.8 GW
Active in queue417.8 GW2,226 requests
Agreement signed76.1 GW459 requests
Withdrawn3,516554.5 GW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

2,226 requests · page 6 of 45
ProjectCapacityStatusLocationRegionQueuedOnline
Red Egret BESS
Battery storage · Red Egret LLC
311 MWAgreement signed Galveston, TXERCOT Mar 2022target 2026
Oak Tree Energy Storage
Battery storage · Live Oak Energy Storage, LLC
310 MWIn study Lavaca, TXERCOT Dec 2023target 2029
Benton Energy Storage II
Battery storage · Xcel Energy
310 MWIn study Benton, MNMISO Aug 2025target 2028
Brickyard Energy Storage
Battery storage · Brickyard Energy Storge, LLC
310 MWIn study Boone, INMISO Aug 2025target 2028
Two Forks BESS
Battery storage · Two Forks LLC
310 MWAgreement signed Cooke, TXERCOT Jan 2022target 2027
Platinum Storage
Battery storage · Platinum Energy Storage LLC
310 MWAgreement signed Fannin, TXERCOT Sep 2021target 2026
Key Storage 1
Battery storage
309 MWAgreement signed Fresno, CACAISO Apr 2018target 2026
Harmony Storage 2
Battery storage
308 MWIn study Contra Costa, CACAISO Apr 2021target 2031
Jackrabbit Power Bank
Battery storage
308 MWIn study Santa Clara, CACAISO Apr 2023target 2029
Larkspur Energy Storage
Battery storage · Larkspur Energy Storage LLC
308 MWAgreement signed Upton, TXERCOT Aug 2021target 2027
Clay County Yang Storage
Battery storage · DM-CCY, LLC
308 MWIn study Clay, TXERCOT Dec 2024target 2028
Mensa BESS
Battery storage · BRP Mensa BESS LLC
307 MWIn study Pecos, TXERCOT Jun 2020target 2027
18-Alpha BESS
Battery storage · SCOUT ENERGY MANAGEMENT, LLC
307 MWIn study Cooke, TXERCOT Apr 2025target 2028
Haute Stockage
Battery storage
307 MWPaused / redesign Shackelford, TXERCOT Oct 2023target 2027
Team Ranch Storage
Battery storage · BAF Storage, LLC
307 MWIn study Tarrant, TXERCOT Jun 2024target 2027
Beaujolais BESS
Battery storage
307 MWPaused / redesign Lamar, TXERCOT Dec 2023target 2026
Axtell BESS
Battery storage · Axtell BESS LLC
307 MWIn study Mclennan, TXERCOT Oct 2024target 2029
Copperleaf Energy Storage
Battery storage · Copperleaf Energy Storage, LLC
307 MWIn study Wichita, TXERCOT Nov 2024target 2029
Gilleys Energy Storage
Battery storage · Gilleys Energy Storage, LLC
306 MWIn study Wise, TXERCOT Jun 2024target 2028
McCrae Energy Storage
Battery storage · McCrae Energy Storage, LLC
306 MWAgreement signed Erath, TXERCOT May 2024target 2028
O'Bannion Energy Storage
Battery storage · O'Bannion Energy Storage, LLC
306 MWAgreement signed Jack, TXERCOT May 2024target 2028
Wooderson Energy Storage
Battery storage · Wooderson Energy Storage, LLC
306 MWIn study Jack, TXERCOT May 2024target 2028
Southfork Energy Storage
Battery storage · Southfork Energy Storage, LLC
306 MWIn study Kimble, TXERCOT Jul 2024target 2028
Blue Skies BESS
Battery storage · ACTX BESS Project LLC
306 MWAgreement signed Hill, TXERCOT May 2022target 2027
Spur Energy Storage
Battery storage · Spur Energy Storage, LLC
306 MWIn study Wise, TXERCOT Feb 2025target 2028
Aurora Energy Storage
Battery storage · Aurora Energy Storage, LLC
306 MWIn study Lampasas, TXERCOT Feb 2025target 2028
Lite Brite Battery Storage
Battery storage
306 MWAgreement signed Suffolk, MAISO-NE Jul 2021target 2028
Humidor Storage 1
Battery storage
305 MWAgreement signed Los Angeles, CACAISO Apr 2019target 2028
Gnarly Osage
Battery storage
304 MWIn study San Diego, CACAISO Apr 2021target 2027
Twinkle
Battery storage
304 MWIn study San Bernardino, CACAISO Apr 2023target 2031
Furay Battery Energy Storage System
Battery storage · Blue Topaz 1, LLC
304 MWIn study Harris, TXERCOT Sep 2022target 2027
NavBoot BESS
Battery storage · Navboot BESS LLC
304 MWAgreement signed Nueces, TXERCOT Mar 2023target 2026
Juanita Creek BESS
Battery storage · Juanita Creek Energy Center, LLC
304 MWIn study Matagorda, TXERCOT Jun 2025target 2031
BRP Aras BESS
Battery storage · BRP Aras BESS LLC
304 MWIn study Upton, TXERCOT May 2021target 2028
Wander Waters BESS
Battery storage · Wander Waters BESS LLC
304 MWIn study Wilbarger, TXERCOT Mar 2024target 2027
Roccasecca BESS
Battery storage
303 MWAgreement signed Clark, NVCAISO May 2016target 2026
Brantley Branch Batt
Battery storage · Brantley Branch LLC
302 MWIn study Rusk, TXERCOT May 2020target 2029
Elion Energy Storage
Battery storage
302 MWAgreement signed Los Angeles, CACAISO Apr 2021target 2034
Tyrell Energy Storage
Battery storage
302 MWAgreement signed Orange, CACAISO Apr 2021target 2032
Tabla Energy Storage
Battery storage
302 MWAgreement signed Los Angeles, CACAISO Apr 2021target 2032
Outrider BESS
Battery storage · Sanders Hollow Energy Center, LLC
302 MWIn study Dickens, TXERCOT Jun 2025target 2028
Dairyland Storage
Battery storage · ENGIE IR Holdings LLC
302 MWIn study Hopkins, TXERCOT Apr 2025target 2029
BRP Passu BESS
Battery storage · BRP Passu BESS LLC
302 MWIn study Wilbarger, TXERCOT Dec 2020target 2028
Simsboro Storage
Battery storage · Simsboro Storage LLC
302 MWIn study Freestone, TXERCOT Jun 2025target 2029
Crater BESS
Battery storage · BRP Crater BESS LLC
302 MWIn study Howard, TXERCOT May 2020target 2028
Rubicon Power BESS
Battery storage · Rubicon Power LLC
301 MWIn study Brazoria, TXERCOT Nov 2023target 2026
Quela BESS
Battery storage · BRP Quela BESS LLC
301 MWIn study Bexar, TXERCOT Sep 2020target 2027
Seine BESS
Battery storage · BRP Seine BESS LLC
301 MWAgreement signed Foard, TXERCOT Dec 2020target 2027
Cernan BESS
Battery storage · Scarlet BESS LLC
301 MWIn study Wharton, TXERCOT Feb 2025target 2027
Acker BESS
Battery storage · Ogallala BESS LLC
301 MWAgreement signed Castro, TXERCOT Jun 2023target 2028
Page 6 of 45

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines · Planned power plants (EIA)