🔌 EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more → Skip to main content

United States › Grid › Interconnection queues › Louisiana

OCTARY USA · INTERCONNECTION QUEUES

Withdrawn queue requests in Louisiana — page 6

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown31059.6 GW
Active in queue37.6 GW140 requests
Agreement signed3,056 MW18 requests
Withdrawn31059.6 GW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

310 requests · page 6 of 7
ProjectCapacityStatusLocationRegionQueuedOnline
Solar project J676, West Baton Rouge Parish, La County
Solar
50.0 MWWithdrawn / abandoned West Baton Rouge Parish, La, LAMISO Jul 2016target 2017
Solar project J633, Jefferson Davis Parish County
Solar
50.0 MWWithdrawn / abandoned Jefferson Davis Parish, LAMISO May 2016target 2018
Battery storage project J1236, St. Landry Parish County
Battery storage
50.0 MWWithdrawn / abandoned St. Landry Parish, LAMISO Apr 2019target 2022
Solar + storage project J3839, Union Parish County
Solar + storage
50.0 MWWithdrawn / abandoned Union Parish, LAMISO May 2024target 2028
Battery storage project J2011, Morehouse Parish County
Battery storage
50.0 MWWithdrawn / abandoned Morehouse Parish, LAMISO Aug 2021target 2025
Solar project J639, West Baton Rouge Parish, La County
Solar
50.0 MWWithdrawn / abandoned West Baton Rouge Parish, La, LAMISO Jun 2017target 2020
Solar project J659, Franklin Parish County
Solar
50.0 MWWithdrawn / abandoned Franklin Parish, LAMISO Jun 2017target 2019
Solar project J616, Ouachita Parish County
Solar
50.0 MWWithdrawn / abandoned Ouachita Parish, LAMISO May 2016target 2019
Solar project J1985, Tangipahoa Parish County
Solar
50.0 MWWithdrawn / abandoned Tangipahoa Parish, LAMISO Nov 2021target 2025
Solar project J660, Richland Parish County
Solar
50.0 MWWithdrawn / abandoned Richland Parish, LAMISO Jul 2016target 2019
Battery storage project J1238, Rapides Parish County
Battery storage
50.0 MWWithdrawn / abandoned Rapides Parish, LAMISO Apr 2019target 2022
Battery storage project J1507, Washington Parish County
Battery storage
50.0 MWWithdrawn / abandoned Washington Parish, LAMISO Jun 2020target 2023
Battery storage project J3176, Plaquemines Parish County
Battery storage
50.0 MWWithdrawn / abandoned Plaquemines Parish, LAMISO Nov 2022target 2026
Battery storage project J3600, Morehouse Parish County
Battery storage
50.0 MWWithdrawn / abandoned Morehouse Parish, LAMISO Apr 2024target 2028
Solar project J619, St. Landry Parish County
Solar
50.0 MWWithdrawn / abandoned St. Landry Parish, LAMISO May 2016target 2018
Solar + storage project J1749, West Baton Rouge Parish, La County
Solar + storage
50.0 MWWithdrawn / abandoned West Baton Rouge Parish, La, LAMISO Jun 2020target 2022
Solar project J1166, Acadia Parish County
Solar
50.0 MWWithdrawn / abandoned Acadia Parish, LAMISO Mar 2018target 2020
Solar project J673, Ouachita Parish County
Solar
50.0 MWWithdrawn / abandoned Ouachita Parish, LAMISO Jul 2016target 2018
Battery storage project J3129, East Feliciana Parish County
Battery storage
50.0 MWWithdrawn / abandoned East Feliciana Parish, LAMISO Sep 2022target 2026
Solar project J559, Washington Parish County
Solar
50.0 MWWithdrawn / abandoned Washington Parish, LAMISO Apr 2016target 2017
Solar project J1433, Washington Parish County
Solar
50.0 MWWithdrawn / abandoned Washington Parish, LAMISO Apr 2019target 2021
Battery storage project GEN-2018-105, Caddo Parish County
Battery storage
50.0 MWWithdrawn / abandoned Caddo Parish, LASPP Nov 2018target 2023
Solar project J664, Avoyelles Parish County
Solar
50.0 MWWithdrawn / abandoned Avoyelles Parish, LAMISO Jul 2016target 2019
Battery storage project J2220, Iberville Parish County
Battery storage
50.0 MWWithdrawn / abandoned Iberville Parish, LAMISO Dec 2021target 2024
Solar project J640, St. Helena Parish County
Solar
50.0 MWWithdrawn / abandoned St. Helena Parish, LAMISO Jun 2017target 2019
Solar project J700, Acadia Parish County
Solar
50.0 MWWithdrawn / abandoned Acadia Parish, LAMISO Aug 2016target 2018
Battery storage project J3178, De Soto Parish County
Battery storage
50.0 MWWithdrawn / abandoned De Soto Parish, LAMISO Sep 2022target 2026
Solar project J2082, Rapides Parish County
Solar
50.0 MWWithdrawn / abandoned Rapides Parish, LAMISO Sep 2021target 2024
Solar project J549, Acadia Parish County
Solar
49.8 MWWithdrawn / abandoned Acadia Parish, LAMISO Mar 2016target 2018
Solar project J551, Concordia Parish County
Solar
49.8 MWWithdrawn / abandoned Concordia Parish, LAMISO Mar 2016target 2018
Solar project J550, Acadia Parish County
Solar
49.8 MWWithdrawn / abandoned Acadia Parish, LAMISO Mar 2016target 2018
Solar project J518, Calcasieu Parish County
Solar
49.5 MWWithdrawn / abandoned Calcasieu Parish, LAMISO Nov 2015target 2017
Solar project J3138, Rapides Parish County
Solar
49.3 MWWithdrawn / abandoned Rapides Parish, LAMISO Sep 2022target 2026
Solar project J3221, Webster Parish County
Solar
49.0 MWWithdrawn / abandoned Webster Parish, LAMISO Sep 2022target 2024
Solar project J645, Lafayette Parish County
Solar
48.8 MWWithdrawn / abandoned Lafayette Parish, LAMISO May 2016target 2018
Onshore wind project J699, St. Mary Parish County
Onshore wind
48.3 MWWithdrawn / abandoned St. Mary Parish, LAMISO Jul 2016
Solar project J665, Morehouse Parish County
Solar
47.5 MWWithdrawn / abandoned Morehouse Parish, LAMISO Jul 2016target 2019
Solar project J674, Morehouse Parish County
Solar
47.5 MWWithdrawn / abandoned Morehouse Parish, LAMISO Jul 2016target 2019
Gas project GEN-2022-185, Caddo Parish County
Gas
46.0 MWWithdrawn / abandoned Caddo Parish, LASPP Feb 20232024
Other project J465, St. Mary Parish County
Other
44.1 MWWithdrawn / abandoned St. Mary Parish, LAMISO May 20152019
Other project J417, Calcasieu Parish County
Other
43.0 MWWithdrawn / abandoned Calcasieu Parish, LAMISO Nov 2014
Other project J2373, Calcasieu Parish County
Other
40.0 MWWithdrawn / abandoned Calcasieu Parish, LAMISO Sep 2022target 2025
Hydro project J324, Grant Parish County
Hydro
36.2 MWWithdrawn / abandoned Grant Parish, LAMISO Mar 2014target 2017
Hydro project J2831, Natchitoches Parish County
Hydro
36.0 MWWithdrawn / abandoned Natchitoches Parish, LAMISO Sep 2022target 2027
Solar project J635, Concordia Parish County
Solar
35.0 MWWithdrawn / abandoned Concordia Parish, LAMISO May 2016target 2018
Gas project GEN-2024-126, Caddo Parish County
Gas
32.7 MWWithdrawn / abandoned Caddo Parish, LASPP Mar 2025target 2027
Battery storage project J1290, Evangeline Parish County
Battery storage
25.0 MWWithdrawn / abandoned Evangeline Parish, LAMISO Apr 2019target 2022
Battery storage project J2109, St. James Parish County
Battery storage
25.0 MWWithdrawn / abandoned St. James Parish, LAMISO Aug 2021target 2025
Solar project GEN-2023-030, Desoto Parish County
Solar
25.0 MWWithdrawn / abandoned Desoto Parish, LASPP Oct 2023target 2027
Solar project GEN-2019-080, Natchitoches Parish County
Solar
25.0 MWWithdrawn / abandoned Natchitoches Parish, LASPP Apr 2019target 2021

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines · Planned power plants (EIA)