SOLAR Β· MISOSolar project J659, Franklin Parish County
Solar project J659, Franklin Parish County is a 50.0 MW solar request withdrawn in the MISO interconnection queue, in Franklin Parish County, Louisiana, connecting to Entergy.
Queue statusWithdrawn / abandoned
- PlanningQueued Jun 2017 (completed)
- Withdrawn / abandonedJan 2019 (project stopped here)
- Consented (not reached)
- Construction (not reached)
- Operating (not reached)
- Closed (not reached)
Request details
- Queue ID
- J659
- Grid region
- MISO (Midcontinent)
- Utility / transmission owner
- Entergy
- Connection point (POI)
- Winnsboro to Gilbert 115 kV line
- Location
- Franklin Parish County, Louisiana
- Technology
- Solar: 50.0 MW
- Total requested
- 50.0 MW
- Service type
- Network resource (NRIS)
- Study phase
- Study Phase: GIA; Post GIA Status: Not Started
- Queue status
- Withdrawn
- Entered queue
- 16 June 2017
- Proposed online date
- April 2019
- Withdrawn
- January 2019
Location
Marker shows the centre of Franklin Parish County; the queue data does not give exact sites.
Power plants in Louisiana Β· Transmission lines in Louisiana
Other requests in Franklin Parish County
- Solar + storage project J3082, Franklin Parish CountySolar + storage Β· 135 MW Β· in study
- Solar project J4142, Franklin Parish CountySolar Β· 115 MW Β· in study
- Solar project J2693, Franklin Parish CountySolar Β· 105 MW Β· in study
- Solar project J2385, Franklin Parish CountySolar Β· 179 MW Β· withdrawn
- Solar project J3098, Franklin Parish CountySolar Β· 75.0 MW Β· withdrawn
- Solar project J618, Franklin Parish CountySolar Β· 58.7 MW Β· withdrawn
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem