SOLAR · MISOSolar project J2693, Franklin Parish County
Solar project J2693, Franklin Parish County is a 105 MW solar request in interconnection study in the MISO interconnection queue, in Franklin Parish County, Louisiana, connecting to ENTERGY LOUISIANA.
- PlanningQueued Sep 2022 (current stage)
- Consented (not yet reached)
- Construction (not yet reached)
- OperatingTarget Apr 2027 (not yet reached)
- Closed (not yet reached)
Studies assess what grid upgrades the project would need and who pays for them. A signed interconnection agreement is the main step before construction.
Request details
- Queue ID
- J2693
- Grid region
- MISO (Midcontinent)
- Utility / transmission owner
- ENTERGY LOUISIANA
- Connection point (POI)
- WISNER
- Location
- Franklin Parish County, Louisiana
- Technology
- Solar: 105 MW
- Total requested
- 105 MW
- Service type
- Network resource (NRIS)
- Study phase
- Study Phase: DPP 2; Post GIA Status: Not Started
- Queue status
- Active
- Entered queue
- 14 September 2022
- Proposed online date
- April 2027
Location
Marker shows the centre of Franklin Parish County; the queue data does not give exact sites.
Other requests in Franklin Parish County
- Solar + storage project J3082, Franklin Parish CountySolar + storage · 135 MW · in study
- Solar project J4142, Franklin Parish CountySolar · 115 MW · in study
- Solar project J2385, Franklin Parish CountySolar · 179 MW · withdrawn
- Solar project J3098, Franklin Parish CountySolar · 75.0 MW · withdrawn
- Solar project J618, Franklin Parish CountySolar · 58.7 MW · withdrawn
- Solar project J659, Franklin Parish CountySolar · 50.0 MW · withdrawn
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem