SOLAR Β· MISO

Solar project J635, Concordia Parish County

Solar project J635, Concordia Parish County is a 35.0 MW solar request withdrawn in the MISO interconnection queue, in Concordia Parish County, Louisiana, connecting to Entergy.

Queue statusWithdrawn / abandoned
  1. PlanningQueued May 2016 (completed)
  2. Withdrawn / abandonedJun 2017 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
J635
Grid region
MISO (Midcontinent)
Utility / transmission owner
Entergy
Connection point (POI)
Tap - Entergy 115kV T-line Natchez/South Plantation (ID:668) 1mile from Plantation Sub
Location
Concordia Parish County, Louisiana
Technology
Solar: 35.0 MW
Total requested
35.0 MW
Service type
Network resource (NRIS)
Study phase
Study Phase: GIA; Post GIA Status: Not Started
Queue status
Withdrawn
Entered queue
9 May 2016
Proposed online date
February 2018
Withdrawn
June 2017

Location

Marker shows the centre of Concordia Parish County; the queue data does not give exact sites.

Power plants in Louisiana Β· Transmission lines in Louisiana

Other requests in Concordia Parish County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem