Solar + storage project J2904, Concordia Parish County

Solar + storage project J2904, Concordia Parish County is a 150 MW solar + storage request withdrawn in the MISO interconnection queue, in Concordia Parish County, Louisiana, connecting to ENTERGY LOUISIANA.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Sep 2022 (completed)
  2. Withdrawn / abandonedJul 2025 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
J2904
Grid region
MISO (Midcontinent)
Utility / transmission owner
ENTERGY LOUISIANA
Connection point (POI)
PLANTATION
Location
Concordia Parish County, Louisiana
Technology
Solar: 150 MW Β· Battery
Total requested
150 MW
Service type
Network resource (NRIS)
Study phase
Study Phase: DPP 2; Post GIA Status: Not Started
Queue status
Withdrawn
Entered queue
9 September 2022
Proposed online date
June 2025
Withdrawn
July 2025

Location

Marker shows the centre of Concordia Parish County; the queue data does not give exact sites.