SOLAR Β· MISO

Solar project J565, Concordia Parish County

Solar project J565, Concordia Parish County is a 102 MW solar request withdrawn in the MISO interconnection queue, in Concordia Parish County, Louisiana.

Queue statusWithdrawn / abandoned
  1. PlanningQueued May 2016 (completed)
  2. Withdrawn / abandonedSep 2016 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
J565
Grid region
MISO (Midcontinent)
Connection point (POI)
Unknown
Location
Concordia Parish County, Louisiana
Technology
Solar: 102 MW
Total requested
102 MW
Study phase
Feasibility
Queue status
Withdrawn
Entered queue
6 May 2016
Proposed online date
April 2019
Withdrawn
September 2016

Location

Marker shows the centre of Concordia Parish County; the queue data does not give exact sites.

Power plants in Louisiana Β· Transmission lines in Louisiana

Other requests in Concordia Parish County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem