United States β€Ί Grid β€Ί Interconnection queues β€Ί Louisiana

BATTERY STORAGE Β· SPP

Battery storage project GEN-2018-105, Caddo Parish County

Battery storage project GEN-2018-105, Caddo Parish County is a 50.0 MW battery storage request withdrawn in the SPP interconnection queue, in Caddo Parish County, Louisiana, connecting to AEP.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Nov 2018 (completed)
  2. Withdrawn / abandonedMay 2022 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
GEN-2018-105
Grid region
SPP (Southwest Power Pool)
Utility / transmission owner
AEP
Connection point (POI)
Longwood 345kV
Location
Caddo Parish County, Louisiana
Technology
Battery: 50.0 MW
Total requested
50.0 MW
Service type
NRIS and ERIS
Study phase
WITHDRAWN
Queue status
Withdrawn
Entered queue
21 November 2018
Proposed online date
December 2023
Withdrawn
May 2022

Location

Marker shows the centre of Caddo Parish County; the queue data does not give exact sites.

Power plants in Louisiana Β· Transmission lines in Louisiana

Other requests in Caddo Parish County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem