United States β€Ί Grid β€Ί Interconnection queues β€Ί Louisiana

SOLAR Β· MISO

Solar project J559, Washington Parish County

Solar project J559, Washington Parish County is a 50.0 MW solar request withdrawn in the MISO interconnection queue, in Washington Parish County, Louisiana.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Apr 2016 (completed)
  2. Withdrawn / abandonedMay 2017 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
J559
Grid region
MISO (Midcontinent)
Connection point (POI)
EEL Holton - Franklinton 115kV
Location
Washington Parish County, Louisiana
Technology
Solar: 50.0 MW
Total requested
50.0 MW
Study phase
GIA
Queue status
Withdrawn
Entered queue
26 April 2016
Proposed online date
October 2017
Withdrawn
May 2017

Location

Marker shows the centre of Washington Parish County; the queue data does not give exact sites.

Power plants in Louisiana Β· Transmission lines in Louisiana

Other requests in Washington Parish County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem