United States › Grid › Interconnection queues › Kentucky
OCTARY USA · INTERCONNECTION QUEUESWithdrawn queue requests in Kentucky — page 6
Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.
Map
Requests
| Project | Capacity | Status |
|---|---|---|
| Solar + storage project AG2-179, Adair County Solar + storage · Round Trip, LLC |
60.0 MW | Withdrawn / abandoned |
| Solar project LGE-GIS-2019-026, Mason County Solar |
60.0 MW | Withdrawn / abandoned |
| Solar project AH2-222 Solar |
60.0 MW | Withdrawn / abandoned |
| Solar project LGE-GIS-2018-005, Mclean County Solar |
60.0 MW | Withdrawn / abandoned |
| Solar project AH1-455, Magoffin County Solar |
60.0 MW | Withdrawn / abandoned |
| Onshore wind project W3-051, Pike County Onshore wind |
60.0 MW | Withdrawn / abandoned |
| Solar project AH1-409 Solar |
58.0 MW | Withdrawn / abandoned |
| Solar project AF2-246, Hardin County Solar |
58.0 MW | Withdrawn / abandoned |
| Sunflower Prairie Solar · Sunflower Prairie Solar Project, LLC |
57.0 MW | Withdrawn / abandoned |
| Solar project J2147, Daviess County Solar |
56.0 MW | Withdrawn / abandoned |
| Solar + storage project AG1-096, Hardin County Solar + storage |
55.0 MW | Withdrawn / abandoned |
| Solar project AD2-107, Perry County Solar |
55.0 MW | Withdrawn / abandoned |
| Wood Duck 100 MW Solar · Wood Duck Solar LLC |
55.0 MW | Withdrawn / abandoned |
| Solar project AF1-267, Madison County Solar |
54.0 MW | Withdrawn / abandoned |
| Solar + storage project AG2-160, Adair County Solar + storage |
53.0 MW | Withdrawn / abandoned |
| Battery storage project AG2-553, Bullitt County Battery storage · EDP Renewables North America LLC |
50.0 MW | Withdrawn / abandoned |
| Solar project AG1-352, Boyle County Solar |
50.0 MW | Withdrawn / abandoned |
| Solar + storage project J2145, Ohio County Solar + storage |
50.0 MW | Withdrawn / abandoned |
| Hart Solar Solar · Thoroughbred Solar, LLC |
50.0 MW | Withdrawn / abandoned |
| Other project V3-055, Perry County Other |
50.0 MW | Withdrawn / abandoned |
| Battery storage project AH2-224 Battery storage |
50.0 MW | Withdrawn / abandoned |
| Solar + storage project AH1-418, Pike County Solar + storage |
50.0 MW | Withdrawn / abandoned |
| Solar + storage project AG2-598, Metcalfe County Solar + storage |
50.0 MW | Withdrawn / abandoned |
| Solar project LGE-GIS-2020-001, Madison County Solar |
50.0 MW | Withdrawn / abandoned |
| Solar + storage project J3794, Daviess County Solar + storage |
50.0 MW | Withdrawn / abandoned |
| Solar project LGE-GIS-2024-003, Croydon County Solar |
50.0 MW | Withdrawn / abandoned |
| Solar project AG2-679, Letcher County Solar |
50.0 MW | Withdrawn / abandoned |
| Solar project AC2-114, Campbell County Solar |
49.9 MW | Withdrawn / abandoned |
| Solar project J2146, Hopkins County Solar |
45.0 MW | Withdrawn / abandoned |
| Solar + storage project J2836, Livingston County Solar + storage |
45.0 MW | Withdrawn / abandoned |
| Wood Duck 100 MW Solar · Wood Duck Solar LLC |
45.0 MW | Withdrawn / abandoned |
| Solar project AG2-183, Hardin County Solar |
45.0 MW | Withdrawn / abandoned |
| Solar + storage project AG2-158, Russell County Solar + storage |
44.0 MW | Withdrawn / abandoned |
| Solar project AH1-082, Metcalfe County Solar · Wildrye Solar LLC |
44.0 MW | Withdrawn / abandoned |
| Solar project 526, Fulton County Solar |
40.0 MW | Withdrawn / abandoned |
| Solar project J1600, Meade County Solar |
40.0 MW | Withdrawn / abandoned |
| Solar project AH1-156, Bourbon County Solar |
40.0 MW | Withdrawn / abandoned |
| Solar + storage project AH2-276, Pike County Solar + storage |
40.0 MW | Withdrawn / abandoned |
| Solar project AG2-549, Hardin County Solar |
40.0 MW | Withdrawn / abandoned |
| Battery storage project AH1-428, Boone County Battery storage · ACE Development Company, LLC |
40.0 MW | Withdrawn / abandoned |
| Solar project AG1-067, Barren County Solar |
38.0 MW | Withdrawn / abandoned |
| Solar project AH1-532, Marion County Solar |
37.8 MW | Withdrawn / abandoned |
| Solar project LGE-GIS-2017-001, Hickman County Solar |
35.0 MW | Withdrawn / abandoned |
| Solar project LGE-GIS-2017-003, Harrison County Solar |
35.0 MW | Withdrawn / abandoned |
| Solar project AG1-208, Montgomery County Solar |
35.0 MW | Withdrawn / abandoned |
| Solar + storage project J2820, Daviess County Solar + storage |
35.0 MW | Withdrawn / abandoned |
| Solar + storage project AG2-317, Barren County Solar + storage |
35.0 MW | Withdrawn / abandoned |
| Solar + storage project J2821, Crittenden County Solar + storage |
30.0 MW | Withdrawn / abandoned |
| Gas project LGE-GIS-2011-002, Jefferson County Gas |
30.0 MW | Withdrawn / abandoned |
| Solar + storage project AF1-219, Boyle County Solar + storage |
30.0 MW | Withdrawn / abandoned |
Capacity in the queue by state
Click a state to drill down.
By grid region
ISO/RTO markets and the non-ISO West and Southeast.
- Southeast (non-ISO utilities)134 · 36.0 GW
- PJM (Mid-Atlantic, Midwest)147 · 18.3 GW
- MISO (Midcontinent)52 · 9,678 MW
Requests by year joined
Capacity of requests in this view, by the year they entered the queue. Click a year.
Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines · Planned power plants (EIA)