🔌 EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more → Skip to main content

United States › Grid › Interconnection queues › Kentucky

OCTARY USA · INTERCONNECTION QUEUES

Withdrawn queue requests in Kentucky — page 6

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown33364.0 GW
Active in queue21.5 GW134 requests
Agreement signed7,260 MW36 requests
Withdrawn33364.0 GW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

333 requests · page 6 of 7
ProjectCapacityStatusLocationRegionQueuedOnline
Solar + storage project AG2-179, Adair County
Solar + storage · Round Trip, LLC
60.0 MWWithdrawn / abandoned Adair, KYPJM Mar 2025target 2023
Solar project LGE-GIS-2019-026, Mason County
Solar
60.0 MWWithdrawn / abandoned Mason, KYSoutheast May 2019target 2021
Solar project AH2-222
Solar
60.0 MWWithdrawn / abandoned KYPJM Mar 2022target 2026
Solar project LGE-GIS-2018-005, Mclean County
Solar
60.0 MWWithdrawn / abandoned Mclean, KYSoutheast Oct 2018target 2022
Solar project AH1-455, Magoffin County
Solar
60.0 MWWithdrawn / abandoned Magoffin, KYPJM Sep 2021target 2025
Onshore wind project W3-051, Pike County
Onshore wind
60.0 MWWithdrawn / abandoned Pike, KYPJM Aug 2010target 2013
Solar project AH1-409
Solar
58.0 MWWithdrawn / abandoned KYPJM Sep 2021target 2024
Solar project AF2-246, Hardin County
Solar
58.0 MWWithdrawn / abandoned Hardin, KYPJM Mar 2020target 2023
Sunflower Prairie
Solar · Sunflower Prairie Solar Project, LLC
57.0 MWWithdrawn / abandoned Mclean, KYPJM Sep 2020target 2024
Solar project J2147, Daviess County
Solar
56.0 MWWithdrawn / abandoned Daviess, KYMISO Nov 2021target 2024
Solar + storage project AG1-096, Hardin County
Solar + storage
55.0 MWWithdrawn / abandoned Hardin, KYPJM Aug 2020target 2023
Solar project AD2-107, Perry County
Solar
55.0 MWWithdrawn / abandoned Perry, KYPJM Mar 2018target 2021
Wood Duck 100 MW
Solar · Wood Duck Solar LLC
55.0 MWWithdrawn / abandoned Barren, KYPJM Jul 2020target 2024
Solar project AF1-267, Madison County
Solar
54.0 MWWithdrawn / abandoned Madison, KYPJM Sep 2019target 2022
Solar + storage project AG2-160, Adair County
Solar + storage
53.0 MWWithdrawn / abandoned Adair, KYPJM Feb 2021target 2023
Battery storage project AG2-553, Bullitt County
Battery storage · EDP Renewables North America LLC
50.0 MWWithdrawn / abandoned Bullitt, KYPJM Mar 2025target 2024
Solar project AG1-352, Boyle County
Solar
50.0 MWWithdrawn / abandoned Boyle, KYPJM Sep 2020target 2023
Solar + storage project J2145, Ohio County
Solar + storage
50.0 MWWithdrawn / abandoned Ohio, KYMISO Nov 2021target 2024
Hart Solar
Solar · Thoroughbred Solar, LLC
50.0 MWWithdrawn / abandoned Hart, KYPJM Mar 2020target 2022
Other project V3-055, Perry County
Other
50.0 MWWithdrawn / abandoned Perry, KYPJM Oct 2009target 2013
Battery storage project AH2-224
Battery storage
50.0 MWWithdrawn / abandoned KYPJM Mar 2022target 2026
Solar + storage project AH1-418, Pike County
Solar + storage
50.0 MWWithdrawn / abandoned Pike, KYPJM Sep 2021target 2025
Solar + storage project AG2-598, Metcalfe County
Solar + storage
50.0 MWWithdrawn / abandoned Metcalfe, KYPJM Mar 2021target 2025
Solar project LGE-GIS-2020-001, Madison County
Solar
50.0 MWWithdrawn / abandoned Madison, KYSoutheast Oct 2020target 2024
Solar + storage project J3794, Daviess County
Solar + storage
50.0 MWWithdrawn / abandoned Daviess, KYMISO Apr 2024target 2028
Solar project LGE-GIS-2024-003, Croydon County
Solar
50.0 MWWithdrawn / abandoned Croydon, KYSoutheast Mar 2024target 2027
Solar project AG2-679, Letcher County
Solar
50.0 MWWithdrawn / abandoned Letcher, KYPJM Mar 2021target 2024
Solar project AC2-114, Campbell County
Solar
49.9 MWWithdrawn / abandoned Campbell, KYPJM Mar 2017target 2019
Solar project J2146, Hopkins County
Solar
45.0 MWWithdrawn / abandoned Hopkins, KYMISO Nov 2021target 2024
Solar + storage project J2836, Livingston County
Solar + storage
45.0 MWWithdrawn / abandoned Livingston, KYMISO Sep 2022target 2025
Wood Duck 100 MW
Solar · Wood Duck Solar LLC
45.0 MWWithdrawn / abandoned Barren, KYPJM Jul 2020target 2024
Solar project AG2-183, Hardin County
Solar
45.0 MWWithdrawn / abandoned Hardin, KYPJM Feb 2021target 2022
Solar + storage project AG2-158, Russell County
Solar + storage
44.0 MWWithdrawn / abandoned Russell, KYPJM Feb 2021target 2023
Solar project AH1-082, Metcalfe County
Solar · Wildrye Solar LLC
44.0 MWWithdrawn / abandoned Metcalfe, KYPJM Jul 2021target 2024
Solar project 526, Fulton County
Solar
40.0 MWWithdrawn / abandoned Fulton, KYSoutheast Nov 2022
Solar project J1600, Meade County
Solar
40.0 MWWithdrawn / abandoned Meade, KYMISO Jun 2020target 2022
Solar project AH1-156, Bourbon County
Solar
40.0 MWWithdrawn / abandoned Bourbon, KYPJM Aug 2021target 2026
Solar + storage project AH2-276, Pike County
Solar + storage
40.0 MWWithdrawn / abandoned Pike, KYPJM Mar 2022target 2024
Solar project AG2-549, Hardin County
Solar
40.0 MWWithdrawn / abandoned Hardin, KYPJM Mar 2021target 2022
Battery storage project AH1-428, Boone County
Battery storage · ACE Development Company, LLC
40.0 MWWithdrawn / abandoned Boone, KYPJM Sep 2021target 2026
Solar project AG1-067, Barren County
Solar
38.0 MWWithdrawn / abandoned Barren, KYPJM Jul 2020target 2023
Solar project AH1-532, Marion County
Solar
37.8 MWWithdrawn / abandoned Marion, KYPJM Sep 2021target 2025
Solar project LGE-GIS-2017-001, Hickman County
Solar
35.0 MWWithdrawn / abandoned Hickman, KYSoutheast Feb 2017target 2019
Solar project LGE-GIS-2017-003, Harrison County
Solar
35.0 MWWithdrawn / abandoned Harrison, KYSoutheast Apr 2017target 2021
Solar project AG1-208, Montgomery County
Solar
35.0 MWWithdrawn / abandoned Montgomery, KYPJM Sep 2020target 2022
Solar + storage project J2820, Daviess County
Solar + storage
35.0 MWWithdrawn / abandoned Daviess, KYMISO Sep 2022target 2025
Solar + storage project AG2-317, Barren County
Solar + storage
35.0 MWWithdrawn / abandoned Barren, KYPJM Mar 2021target 2024
Solar + storage project J2821, Crittenden County
Solar + storage
30.0 MWWithdrawn / abandoned Crittenden, KYMISO Sep 2022target 2025
Gas project LGE-GIS-2011-002, Jefferson County
Gas
30.0 MWWithdrawn / abandoned Jefferson, KYSoutheast Feb 2011target 2015
Solar + storage project AF1-219, Boyle County
Solar + storage
30.0 MWWithdrawn / abandoned Boyle, KYPJM Sep 2019target 2022

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines · Planned power plants (EIA)