United States βΊ Grid βΊ Interconnection queues βΊ Kentucky
BATTERY STORAGE Β· PJMBattery storage project AH1-428, Boone County
Battery storage project AH1-428, Boone County is a 40.0 MW battery storage request withdrawn in the PJM interconnection queue, in Boone County, Kentucky, connecting to EKPC.
Queue statusWithdrawn / abandoned
- PlanningQueued Sep 2021 (completed)
- Withdrawn / abandonedJul 2025 (project stopped here)
- Consented (not reached)
- Construction (not reached)
- Operating (not reached)
- Closed (not reached)
Request details
- Queue ID
- AH1-428
- Grid region
- PJM (Mid-Atlantic, Midwest)
- Utility / transmission owner
- EKPC
- Developer
- ACE Development Company, LLC
- Connection point (POI)
- Tommy Gooch - Garrard County 69 kV
- Location
- Boone County, Kentucky
- Technology
- Battery: 40.0 MW
- Total requested
- 40.0 MW
- Service type
- Network resource (NRIS)
- Study phase
- In Progress (unknown study)
- Queue status
- Withdrawn
- Entered queue
- 10 September 2021
- Proposed online date
- September 2026
- Withdrawn
- July 2025
Location
Marker shows the centre of Boone County; the queue data does not give exact sites.
Other requests in Boone County
- Solar project AH1-239, Boone CountySolar Β· 80.0 MW Β· in study
- Solar project AH1-466, Boone CountySolar Β· 600 MW Β· withdrawn
- Battery storage project AH1-467, Boone CountyBattery storage Β· 300 MW Β· withdrawn
- Solar project AH1-240, Boone CountySolar Β· 200 MW Β· withdrawn
- Solar project AC1-138, Boone CountySolar Β· 2.5 MW Β· withdrawn
- Solar project AC1-137, Boone CountySolar Β· 1.9 MW Β· withdrawn
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem